When are we getting next batch of mlu f-16s from turkey?
PAF F-16 Modernization
As the result of the tender opened by Pakistan Air Force regarding the modernization of 41 F-16 Aircraft, TUSAŞ has been selected as the contractor.
The contract has been signed on 29 June 2009.
The modernization activities started in the last quarter of 2010 by receiving first 3 F-16 to TAI facilities. The total modernization period is anticipated as 47 months and the program is planned to be completed by the year 2014.