China Pakistan Economic Corridor (CPEC) | Power Plants

.-.-.-

Mohmand Dam Hydropower Project to generate low-cost & environment-friendly electricity​

April 5, 2022
PCI



The Chinese Embassy in Islamabad said that the Mohmand Dam Hydropower Project has successfully achieved 1+ milestone through joint efforts of both Chinese & Pakistani workers. Furthermore, this project will add 800MW hydel electricity, contributing 2.86bn units of low-cost & environment-friendly electricity annually to the national grid. In addition, the Mohmand dam project will also provide sustainable water resources for agriculture and human consumption in the province, contributing to national energy and water security.​



.-.-.--.-.-.-.-.-.-
 
.
,.,.

Under Construction Hydropower - Dasu Hydropower Project (4320MW)...

Dasu Dam Stage 1 Completion: 2025
Power Generation of stage 1: 2160 MW

1649338844166.png





1649338865039.png




1649338902077.png

,.,.,.,.,,,...,...,.,
 
.
.,.,,.,.
Under construction Diamer Basha Dam project

Chilas : Under construction in Diamer Basha Dam project area re-located KKH , Shtialthor bypass has been opened for all kinds of traffic from Shtial to Minar Nala Link Road.

This 25 km long highway was opened light traffic on 26 March. RKKH (Alternative Highway) Heavy traffic was turned from Shtial Bypass towards Minar Nala.

All passengers, tourists Karakoram and goods carrying vehicles traveling between Gilgit-Baltistan and Islamabad on Karakoram highway are now on the dam site. Someone Alternative right of way will continue the Karakoram Highway (RKH).

All passengers and heavy transporters traveling on RKKH (Alternative Karakoram Highway ) are appealed to drive carefully according to the instructions listed on the signboard installed on the highway.

Local and international transporters have expressed happiness over the traffic restoration at KKH.

This highway, which was built with more than Rs 78 crore, is 7.3 meters while width 9.8 meters.

At this time, construction activities on eight sites at Diamer Basha Dam are continuing rapidly. ں. Total 8.1 million acres of water storage capacity.

The dam will generate 4500MW cheaper and environmentally friendly electricity.


1649700093025.png




1649700109279.png


,.,.,.,
 
.
,.,.,.,.,.
884MW - Suki Kinari HPP (under construction,,,,
The construction activities are in progress with severe weather conditions.
The civil and electro-mechanical works are going on.


1649765855963.png




1649765873321.png





1649765903186.png




1649765929233.png

,.,..,
 
.
.,.,,.,.,
Mohmand Dam Hydropower Project - 800 MW
Under Construction since September 2019
Gross Storage....... 1.2 MAF
Annual Energy Production....... 2,862 GWh
Completion date...: 2025.

1650024662949.png



1650024707899.png



1650024733623.png




1650024780959.png

.,.,
 
. . .
Diamer Bahsha Dam... works continue during night........

1650196155588.png
 
.
,.,.,.
Prime Minister Shehbaz Sharif says Diamer Bhasha Dam is a vital project for power generation, water storage, creating job opportunities and further strengthening the economy.

He expressed these views during his visit to the construction site of the dame in GilgitBaltistan today [Sunday].

The Prime Minister reviewed the ongoing work on the dam and talked to the workers.

He asked the Chief Secretary and Chairman WAPDA to finalize a proposal for a 300-bed hospital within one week. He also announced construction of 13km Babusar top tunnel from Naran to Chillas to ensure year’s round traffic flow and asked the authorities to submit a study report to his office.

The Prime Minister asked the team to expedite work to complete this project till 2026 instead of 2029.

The Prime Minister expressed satisfaction on the pace and standard of the construction work and said that it will expedite economic activities in the whole area.

Chairman WAPDA retired Lt. General Muzammil Hussain briefed the Prime Minister on the ongoing construction work.
The Premier was accompanied by PML-N leaders Marriyum Aurangzeb, Shahid Khaqan Abbassi and Khwaja Muhammad Asif...
.....
 
.
.,.,.,.
Concrete pouring being carried out at Bridge No. 2 at Diamer Bhasha Hydropower Project site.

1650229332626.png




1650229286787.png

,.,.,.,.
 
.
,.
Alleviating Pakistan’s energy shortage

Energy shortage is a hard nut to crack which restricts the economic development of Pakistan. It is a problem that previous Pakistani governments attached great importance to and desperate to solve. The electricity gap cost Pakistan an annual average loss of US$13.5 billion in GDP, according to a study by PwC in 2012. Power shortage left Pakistan in the dark for a long time, with rolling blackouts across the country lasting about 10 hours a day in major cities and up to 22 hours in rural areas.

CPEC has regarded the alleviation of energy shortage in Pakistan as one of the important areas of construction since its launch. Currently, 12 projects with a total installed capacity of 7,240 MW have been commenced or put into operation. Through five years of construction, energy projects under the CPEC framework added 3,340 MW of electricity to Pakistan by early April 2019, accounting for 11% of the country’s total installed electricity capacity, thus greatly alleviating the power shortage in Pakistan.

In addition to power generation projects, China built the Matiari–Lahore ±660kV HVDC Transmission Line Project in Pakistan- the second HVDC transmission line in the world- to address the aging of Pakistan’s power grid.
,.
 
.
.,.,.,
Congratulations on the successful Signing Ceremony of Provisional Acceptance for K-3, another cooperation project between China and Pakistan.

K-2 and K-3 will provide nearly 20 bn Kwh of clean electricity to Pakistan annually, equivalent to reducing CO2 emissions by 16.32 million tons.

1650417326234.png



1650417349082.png




1650417381709.png
 
. .
.
,.,.,.,.
Under Construction Karot Hydropower Project - 720MW
Located on Jhelum river and first Hydel Project of CPEC.
The Project is in his final stage and soon first unit will be commissioned.


1650977395131.png




1650977422424.png




1650977448009.png





1650977475026.png
 
.