China Pakistan Economic Corridor (CPEC) | Power Plants

...

Pakistan seeks Bahrain’s investment in CPEC energy sector..​

1646261625627.png

.
A long-term plan is being worked out to transform bilateral ties between Pakistan and Bahrain into a strong economic partnership to create a win-win situation for both countries, said Pakistan’s Ambassador to Bahrain Muhammad Ayub.

“I see a lot of mutually beneficial opportunities in the areas of trade, investment, food security, energy, tourism, higher education, training and development,” said the envoy in an exclusive interview.

He highlighted that the China-Pakistan Economic Corridor (CPEC) offered enormous opportunities to investors from Bahrain, especially in the field of energy.

“Pakistan’s geostrategic location makes it a regional economic hub and an energy corridor,” he said. “Likewise, Bahrain’s location makes it an ideal gateway for the Gulf Cooperation Council (GCC) countries.”

While citing that Pakistan was an attractive tourist destination, he invited businessmen from Bahrain to explore the local scenic beauty and benefit from the huge investment opportunities in the sector.

He particularly pointed towards infrastructure projects such as hotels, resorts and parks. “Reciprocally, efforts are also being made to bring tourists from Pakistan to Bahrain.”

Talking about the investment opportunities in food industry, the envoy said that Bahraini investors could pour investment into food storage, processing, packaging and transportation in Pakistan to earn significant profit.
 
.
...
Mohmand Dam Hydropower Project - 800 MW
Under Construction since September 2019
Gross Storage 1.2 MAF
Annual Energy Production 2,862 GWh
Completion date: 2025…

1646352541354.png

...


1646352568189.png


..

1646352602715.png
 
.
CHINA / DIPLOMACY

Pakistan power project using China’s Hualong One connected to grid

By Global Times Published: Mar 05, 2022 12:39 AM


Photo: China National Nuclear Corp

Photo: China National Nuclear Corp

The K-3 unit of the Karachi Nuclear Power Project in Pakistan, the fourth entity to use a China-designed third-generation nuclear reactor, was successfully connected to the grid on Friday, laying solid foundations for commercial operation.

All four of the units adopting China’s Hualong One nuclear reactor are now connected to the grid and are generating electricity, China National Nuclear Corp (CNNC) said in a statement on Friday.

Each Hualong One unit is expected to generate nearly 10 billion kWh of electricity annually after being completed, which can meet the annual electricity demand of more than 4 million households in Pakistan – equivalent to reducing use of standard coal by 3.12 million tons, and reducing carbon dioxide emissions by 8.16 million tons every year. It is also the equivalent of planting more than 70 million trees, CNNC said.

It is of great significance for optimizing Pakistan's energy structure, as well as reaching carbon peak and carbon neutrality goals, CNNC added.

The success in construction and operation of the nuclear reactors in Pakistan will make the Hualong One technology better received in the global market, especially in countries and regions participating in the Belt and Road Initiative, observers said.

The K-2 unit of the Karachi Nuclear Power Plant in Pakistan, which also uses Hualong One, officially started commercial operation on May 20 last year.

As China's "calling card" for its nuclear power industry, Hualong One has become one of the most widely recognized third-generation nuclear power reactors in the market.

All of Hualong One’s core components are produced domestically, and it has a design life of 60 years and meets the strictest safety standards in the world, according to a report from the Xinhua News Agency.

In May 2015, construction began on the world's first Hualong One demonstration project in Fuqing. On January 30, the world's first nuclear power unit under Hualong One, unit 5 of CNNC's Fuqing nuclear power plant, entered commercial operation.

With Hualong One online, China is now at the world forefront of third-generation nuclear technology, alongside countries like the US, France and Russia, the Xinhua News Agency reported, citing CNNC Chairman Yu Jianfeng.

The commercial use of Hualong One will also help to meet China’s goal for CO2 emissions to peak before 2030 and to achieve carbon neutrality before 2060, Yu added.


Hope this helps keep your electricity bills down :pakistan::china:
 
. .
..
A Scenic view of Surge Shaft area of 884MW Suki Kinari Hydropower Project..

1646921118824.png



1646921146937.png



1646921172387.png



The project is under construction since 2017.
234m deep shaft is located at the end of the 23.2km long headrace tunnel. It has two chambers namely upper and lower chambers while will neutralize the hammering effect of water due to the sudden shutdown of generating units.
Due to poor ground conditions, mechanical excavation and installation of heavy support system including lattice girders and rock anchors are being implemented.
..
 
.
Bin Qasim Plant, BQPS III - 900MW RLNG Based unit 1 GT 1st fire successfully done today ..............

1647371553850.png




1647371576096.png



.....
 
.
...............................................................................................................
Dam site of Suki Kinari Hydropower Project -884MW...



1647463094887.png




1647463141999.png



................
 
. .
,.,
Dasu Hydropower Project..

The first Concrete of the Shear Zone of Diversion Tunnel Began at Dasu Hydropower Project....
Recently, the pouring of first concrete has begun. The pouring of concrete lay down the solid foundation for the subsequent construction of the dam body.


1647694888426.png





1647694854656.png

.,.
 
.
,.
Pakistan Day:
An especially prepared 18x24 feet National Flag flying high at Diamer Basha Dam site on left bank of River Indus on a 100 feet high pole...

1648041616730.png



1648041635296.png




1648041663597.png

,.
 
.
,.,
Under Construction Karot Hydropower Project - 720MW
Located on Jhelum river and first Hydel Project of CPEC.
The Project is in his final stage and soon first unit will be commissioned.


1648728845790.png



1648728869498.png



1648728900473.png

.,.,.,.
 
.
,.,.,
The Suki kinari Hydropower Project is located on the Kunhar River in the beautiful valley of Kaghan, KPK Province.

As a key project in the list of the first batch of priority projects of the "China-Pakistan Economic Corridor", China Energy Construction Gezhouba Group's overseas greenfield investment "first order", the project shoulders the major mission of Gezhouba Group's transformation and upgrading and structural adjustment.

The SK Hydropower Station is equipped with four Pelton turbine generators with a single unit capacity of 221 MW, with a total installed capacity of 884 MW, a maximum net head of 922.72 meters, and an average annual power generation of 3.212 billion kWh for many years.


1648904249399.png





1648904269518.png

.,.,.,.,.,.,.,.,.,.,.,.
 
. . .
,.,.,
A historic Moment at Karot HPP
Karot teams along with NTDC and NPCC successfully commissioned and energised 500kV GIS with National Grid at 0434 hrs. Indeed a great milestone and congratulations to all stakeholders and teams.
Credits: Engr. Arslan & Danish..