What's new

New Islamabad Airport Progress

.
New Islamabad airport: NAB launches inquiry against CAA

By Waqas Naeem Published: November 23, 2012

"Airport does not meet the international standards of using two airstrips simultaneously, as the inter-strip distance is only 300 metres," says Khan.

ISLAMABAD:
The National Accountability Bureau (NAB) has launched an inquiry against the Civil Aviation Authority (CAA) after finding design faults in the new Islamabad airport.
Assessments carried out under the NAB’s Prevention and Awareness Regime revealed that the faulty design at the under-construction airport caused more than Rs1 billion in losses, NAB spokesperson Zafar Iqbal Khan said. The airport is being constructed near Fateh Jang.
Khan said the airport does not meet the international standards of using two airstrips simultaneously, as the inter-strip distance is only 300 metres instead of the recommended 800 metres.
CAA spokesperson Pervez George showed surprise when asked about the airstrip distance. He said the project was being built according to international standards and he does not think such technical mistakes could arise.
NAB Chairman Admiral (retd) Fasih Bukhari has directed the operations divisions to conduct an inquiry into CAA’s negligence.
The CAA is also conducting a study to revisit the charges it collects from international flights operating through the country’s airspace, as well as ground facilities used by domestic and international carriers. The study was initiated after a NAB inquiry into the authority’s auditing and billing system was launched in March.
The NAB inquiry found that the CAA has been losing around Rs10-13 billion every year because it allows free parking to international carriers for six hours. Iqbal said international aviation authorities only allow free parking for two hours, after which carriers are charged at an hourly rate.
If the CAA adopts such a system, it can double its revenue to Rs27 billion, according to NAB.
New Islamabad airport: NAB launches inquiry against CAA – The Express Tribune

This should have been completed by June 2013 but it doesn't seem to be completed by next year.
 
.
New Islamabad airport: delays, cost over-runs

By Engr Hussain Ahmad Siddiqui | From InpaperMagzine | 3rd September, 2012

THE New Islamabad International Airport under construction near Fatehjang, Attock District, which was originally scheduled for completion in December 2010, is now expected to be functional by 2014.

This vital project is a typical case of poor planning, inefficient management and improper monitoring that has resulted in huge cost over-runs, while so far depriving the nation of a world-class airport.

Planned in 1984, it could not take-off due to a variety of factors, as mode of work, project parameters and procedure for award of contract were revised a number of times.

Though the required land of 3,200 acres was acquired in 1980s, the project, which is being implemented by the Civil Aviation Authority (CAA) on self-financing basis, could be announced as late as on January 7, 2005. But, again, there was no progress.

Meanwhile, it was decided to acquire an additional 400-acres of land. The government suffered substantial loss in the deal as land was purchased at very high cost through direct private negotiations. The after-thought of purchase of additional land impacted on the progress of the project.

Finally, the project was launched on April 7, 2007, envisaging completion over three years. Interestingly, this was done without approval of feasibility report, and without conducting an environmental impact assessment (EIA) study, both pre-requisites for commencing construction of a project of this nature and magnitude.

The mandatory EIA report was finalised in September 2010. By this time, the original estimates of Rs18 billion (2005) were already outdated and the construction contracts were awarded in 2007-08 at Rs37 billion. On completion, the project is now estimated to cost about Rs66 billion.

Contract for site preparation and other earthworks was awarded in 2007 at a cost of Rs1.5 billion, to be over in 18 months.

Ironically, this was done in the absence of detailed design and engineering of airport complex. Services of the American consultants were engaged later for development of master plan of airport and its project management, whereas designing of airport infrastructure was assigned to a French company.

Most modern and largest in the country, the green-field airport has been designed in accordance with international standards and practices, employing state-of-the-art facility for wide-body aircrafts of latest generation.

The complex comprises, among other facilities, four rapid-exit taxiways, an apron to accommodate 20 aircraft, a special parking area for ‘hijacked aircraft’, and a 15-gate terminal with 10 remote gates. Its design addresses key issues of safety, security and efficiency.

The airport will provide passenger-friendly services that include 42 immigration counters, nine baggage claim carousels, 12 x-ray machines, car-parking for 2,000 vehicles, a covered plaza area for 200 cars , hotel, convention centre, food court and leisure facilities etc.

Works of airport complex is divided into three categories— airside infrastructure, landside infrastructure and passenger
terminal building.

Contract for airside and landside infrastructure was awarded in August 2008 at sterling 156 million with 24-months completion
period.

The work was suspended by contractor in early 2009, and resumed after almost six months, due to financial constraints, in spite of the fact that contractor was paid Rs1.75 billion as mobilisation advance.

Contract for terminal building, to be completed in 30 months, was awarded simultaneously. Later, overall completion date of project was revised to June 2011 that could not be achieved either.

Progress as on June, 30 2012 on airside infrastructure was 86 per cent and on landside infrastructure 39 per cent. Work is complete on the two runways—one main and other emergency, which will be operated independently, in parallel.

The CAA ran the first test flight to the airport on March 23, 2012 to check its runways. Remaining works related to this contract are now scheduled for completion by December this year.

Passenger terminal building, which is of modular design to enabling further expansion, is in advanced stage of construction, with features similar to that of the Singapore Changi Airport.

The new airport is being built to replace existing overloaded and congested airport at Chaklala, so as to meet growing requirements of air traffic and passenger flow. However, when the airport becomes operational in 2014, it may not have enough capacity to handle the projected passengers and cargo.

The air traffic at Islamabad, is growing at a rapid pace, averaging five per cent annually. In the first phase, the new airport will provide facilities to 3.9 million passengers and handle 50,000 tons cargo.

The parameters have already changed. The total number of passengers, domestic and international at Islamabad airport was 3.14 million in 2008-09 and cargo handled 51,557 tons. Thus, there will be over four million passengers using this airport in 2014.

The new airport will be upgraded in phases to achieve full operational capability to meet traffic of 9.3 million passengers and 80,000 tons cargo, projected up to 2030. Airport facilities are to be expanded beyond 2030.

The government, which has a poor track record of completing large projects within time-schedules, needs to take effective steps to complete the New Benazir Bhutto International Airport, as it is known now, without further delays and cost over-runs.

New Islamabad airport: delays, cost over-runs | DAWN.COM
 
.
news-04.gif
 
.
Harris to install advanced Pakistan systems

Harris Corporation, an international communications and information technology company, has been awarded a contract to install critical air traffic control (ATC) communications at a new international airport in Pakistan.

Through its partner GECI, Harris will supply a primary Liberty-STAR Voice Communication and Control System (VCCS) as well as a back-up system to the new Benazir Bhutto International Airport. The airport, which is currently under construction, will become the largest airport in Pakistan and replace the existing airport in Islamabad sharing the same name.

Liberty-STAR VCCS features a modular architecture, open-platform software and commercial-off-the-shelf hardware that delivers a reliable, scalable communications solution for ATC towers, airline and area control dispatch, flight service stations, and mobile shelters. The system will be equipped with touch-screen operator positions, radio interfaces, telephone interfaces, and a System Maintenance, Administration and Reconfiguration Terminal (SMART) POSITION.

“The new airport will significantly help the region and the country attract more business and solidify their burgeoning economy,” said Carl D’Alessandro, vice president and general manager, Civil Programs, Harris Government Communications Systems. “Harris is pleased to provide the Civil Aviation Authority with a unique, integrated communications solution for their new state-of-the-art facility.”

Harris has extensive experience developing mission-critical solutions that support civil and military air traffic control operations worldwide, including more than 200 customers in more than 50 countries. While this is the company’s first ATC communications contract in Pakistan, Harris has supplied communications systems for a wide range of countries in the Middle East region, including Iraq, Afghanistan, United Arab Emirates, Yemen and Saudi Arabia.

Harris to install advanced Pakistan systems | Air Traffic Management | Air Traffic Management - ATM and CMS Industry online, the latest air traffic control industry, CAA, ANSP, SESAR and NEXTGEN news, events, supplier directory and magazine
 
. .
Is it really needed?I mean this money could be well spent on Electricity Projects - Anyway Gandhara does not sound good in urdu.Pakistan is not a monarchy so New Bhutto International Air Port name will be reversed after PPP Government is gone.It should be named after some Pakistan Independence Movement Hero such as Huseyn Shaheed Suhrawardy.


I was thinking the same thing that do we need another airport the one we have is already enough
Technically the hills around the old airport are difficult for pilots so a Airport outside in open area was recommended


Other then that , yes the 200-1 Billion could have been better used on Solar power
 
.
What is the yearly passenger capacity of this airport
 
. . . . .
6__22_-2838-800-600-80.JPG


1526677_418609864908542_981610549_n.jpg


1471755_418609934908535_1670612998_n.jpg


1486144_788707951146589_982951658_o.jpg


1526920_10151790595297563_583966592_n.jpg


1374763_10151790595922563_711686601_n.jpg


77948_637506739643609_864973043_o.jpg


1401200_637504749643808_357126945_o.jpg

1540500_637504969643786_1198802893_o.jpg


Departure Area

1557461_637508102976806_1801998121_n.jpg


Picture Credits: Habib Construction, Yasir Irfan, Mohammad Bilal, Amna Imran Shah, Asad Ali
 
. .
Wow!! Looks very modern. Will it be able to accommodate A380?
 
.
Back
Top Bottom