What's new

Mohmand Dam Hydropower Project .....800 MW

1623935161665.png




1623935181605.png




1623935205157.png
 

Inaugration of Crushing Plant at Mohmand Dam - 800MW
🏗


The Crushing plant is located at right bank of Swat River. To meet the aggregate requirement for the construction of dam and axillary structures, the plant has been erected which will help to accelrate the construction progress.


1625146537846.png




1625146556659.png
 
On 6th July, 2021, another achievement registered at Mohmand Dam. The Excavation faces breakthrough with each other from Diversion Tunnel no.1.

The diversion tunnels are key line of the project to timely divert the river flow and start the main dam construction. It is pertinent to mention here that to expediate the progress, the working from 4 location on twin diversion tunnels are in progress.


1625701689494.png





1625701711952.png






1625701746103.png
 
Mohmand Dam Project | Construction Activities
July, 2021


Jul 11, 2021



 
Visit of Federal Secretary for Ministry of Water Resource to Mohmand Dam in Lower Mohmand Sub-Division on 14th July.
He was briefed about work progress, land acquisition and security arrangements.
 
Under Construction Mohmand Dam Hydropower Project - 800 MW
Under Construction since September 2019
Gross Storage 1.2 MAF
Annual Energy Production 2,862 GWh
Completion date: 2025


1627335463734.png





1627335488546.png





1627335512456.png
 
On 28th July, 2021, another achievement marked at Mohmand Dam.
The excavation faces breakthrough with each other from Diversion Tunnel no.2. Both tunnel sections breakthrough with high-accuracy alignment.


1627491217663.png





1627491252113.png
 
Mohmand Dam Hydropower Project - 800 MW
Under Construction since September 2019
Gross Storage 1.2 MAF
Annual Energy Production 2,862 GWh
Completion date: 2025


1627738237935.png





1627738264504.png




1627738297675.png




1627738335927.png
 
Two diversion tunnels having 15m diameter are being excavated on the right bank. The excavation and support activities are going on around the clock. To accelerate the diversion of river swat, the tunnels are being excavated from multiple work fronts. The total length of both tunnels is about 3,300m.


1627861716031.png
 

Pakistan Defence Latest Posts

Back
Top Bottom