What's new

Hydro power plants updates

.,.,.
Under Construction Jaggran II Hydropower Project - 48MW. Weir, Water Distribution Assembly and Bifurcators/Manifolds.

Concrete pouring under the Steel liner at Weir Flushing Section “Under Sluice Section”. 16mm thick Steel Liner is installed at the Weir Flushing Section of 48MW Jaggran-II Hydropower Project to resist the extensive abrasion by the sediments. Instead of pouring Abrasion Resistant Concrete, the Designer had proposed the Steel Liner on the “Weir Under Sluice Section” to precipitate the rubbing & bumping impact of large size boulders and gravels which the highly steep-sloped river channel is carrying with it.


1655849912087.png




1655849935140.png




1655849958172.png
 
. . .
.,.,
Gulpur Hydropower Project (102MW)

Chairman NEPRA Mr. Tauseef H. Farooqi visited Gulpur Hydropower Project (102MW).

Gulpur Hydropower Project was constructed by Korea South East Power Co (KOEN) through its subsidiary Mira Power Limited who achieved commercial operations in 2020.
Project was financed by IFC - International Finance Corporation, Asian Development Bank (ADB), KEXIM, CDC and FMO - Dutch entrepreneurial development bank. The Project providing 465KWh clean energy to the National Grid.


1656165659597.png




1656165705529.png




1656165739522.png
 
.
.,.,
84-MW Gorkin-Matiltan Hydropower Project, Swat, KPK ...


1656934775266.png




1656934798650.png




1656934830125.png





1656934862495.png
 
. . . .
,.,.,
Diamer Basha Dam - 4500MW..
Construction works commenced in 2020..
8.1MAF water storage and will irrigate 1.2 million acres agricultural land..
Annual generation 18,097 GWh..
Construction Period: 09 years..

1657972073006.png
 
.
,.,.,
Suki Kinari Hydropower Project located on Kunhar River in beautiful valley of Kaghan, Khyber Pakhtunkhwa.
It will generate over 884 MW electricity, and is expected to be completed by end of 2023.

1658232333806.png





1658232364321.png
 
. .

NTDC to evacuate power from Tarbela 5th extension project​


By Khalid Aziz | Gwadar Pro Jul 29, 2022



ISLAMABAD, July 29 (Gwadar Pro)-The National Transmission and Dispatch Co. (NTDC) has awarded contract for construction of transmission line to evacuate electricity from 1530 megawatts5th extension project at Tarbela dam.
The project, co-financed by World Bank and China-led Asian Infrastructure Investment Bank (AIIB), aims at elevating the level of 5th tunnel of the country’s largest dam to save it from an eminent collapse, and also at the installation of a 1530MWs powerhouse.World Bank will provide $390 million for the project. AIIB has already disbursed its share of $300 million as sovereign loan, with the last tranche issued on June 1, 2022, the multilateral lender said recently.
Contract for the 50-kilometre long 500 kV transmission line was awarded to the Lahore-based NETRACON Technologies, NTDC said on July 27.
The project also includes a 2.8-kilometre-long 500 kV single-circuit transmission line to interconnect the switchyards of T4 and T5 powerhouses, it added. T5 will be connected with the planned 500 kV Islamabad West Grid Station, NTDC further said.
According to AIIB, the project will have an annual generation capacity of 1,800 gigawatt-hours.The total capacity at Tarbela with the induction of Tarbela 5th extension will become 6,298 MWs and annual average generation will increase to 19,000 GWh, it said.
NTDC said that the project will be completed in two years. The addition of low-cost clean and green energy from the project will increase the sustainability of the country’s energy regime, it concluded.

 
.

Koto Hydropower Project to be completed by December 2022​


By Tahir Ali | Gwadar Pro Aug 1, 2022



TIMERGARA, August 1st (Gwadar Pro)-As Pakistan is in dire need of power, the 40.8 MW Koto Hydropower Project in Timergara, Lower Dir will start adding the much-desired green power to the national grid by the end of 2022.
Secretary Energy & Power, Khyber Pakhtunkhwa (KP) Syed Imtiaz Hussain Shah and Chief Executive Officer Pakhtunkhwa Energy Development Organization (PEDO) on Saturday visited Koto Hydro Power to examine the working pace. “Heavy machinery has been installed and the project will be completed in the current year,” as per an official statement released after the visit.
“Koto Hydropower is a key project of PEDO, aimed at cheaper, renewable, environment-friendly power,” said CEO PEDO, keeping in mind the present and future requirements of Pakistan, especially rural and remote areas of the province.
China’s Sichuan-Sarwar-Silian-Chongqing Luyang (JV) is the contractor of the project, which will export 205 GWh of energy annually in the future.
Construction was commenced in February 2015 while the original project completion date was February 2019.
The Koto Hydropower project is highly beneficial due to less unit cost and will help in saving foreign exchange on the import of thermal fuels. Due to the project, annual gas releases of about 71,100 tons of CO2 from an equivalent gas thermal plant and 129560 CO2 from a diesel thermal plant will be avoided.
According to PEDO, the financial benefits of the project over 50 years have been calculated on the proposed Sale Price of Rs.9.63 per kWh. The Financial Internal Rate of Return (FIRR) has been worked out as 12.49 %, which makes the project financially viable.
 
.
,.,.
Under Construction Mohmand Dam Hydro Power Project
Right Bank having a 3.5 km length with a 1km access Tunnel has been started. These tunnels will provide irrigation water to the area and a small powerhouse is proposed to generate 4.3MW power from these tunnels.


1659461465648.png
 
.
Mohmand Dam Project

Under construction tunnel....

1659709712974.png




1659709831322.png
 
.

Country Latest Posts

Back
Top Bottom