What's new

Energy Projects...Updates

@AsimSBajwa

Historic day-Tripartite Agreement signing ceremony for Kohala Hydel Power Project being held today.Largest power sector investment of $2.4 Bn in one IPP. With PM’s clear direction to expedite CPEC projects,all stake holders worked hard to bring this day #CPEC #cpecmakingprogress
2:21 AM · Jun 25, 2020
 
Project Thar Mine Mouth Oracle Power Plant ( 1320MW) & surface mine


Primary Energy Input Thar Coal
Technology Sub Critical

Installed Capacity (MW) 1320

Location Thar Block-VI
Province Sindh

Estimated Cost (US $ Million) Yet to be determined
Executing Company / Sponsors M/s Oracle Coalfields SEPCO and Yanzhou Coal
Coordinating Ministry Ministry of Energy (Power Division)
Supervising Agency Private Power and Infrastructure Board (PPIB)


Project Progress Update
  • Feasibility stage tariff obtained for coal.
  • Shareholding agreement on new equity partners in process.
  • Under issuance of NTP/LOI.
 
103571365_2618301985104986_6015564555960337101_o.jpg
 
720 MW Karot Hydropower Project Under Construction

104474069_2634506813484503_1993949534762803999_n.jpg
 
640 MW MAHL HPP


Introduction

640 MW Mahl Hydropower Project is located 5 km upstream of the confluence of Mahl River with the Jhelum River on the boundary between the state of Azad Jammu & Kashmir (AJK) and the province of Punjab with some portion of dam in the Province of Khyber Pakhtunkhwa (KPK).

Implementation of Mahl project will bring energy security, save foreign exchange in billions of US dollars over the life of the project, create thousands of jobs, stabilize socio economic life style of the people of Pakistan and the State of AJK and provide the much needed energy on a sustainable basis for rapid growth of Pakistan. Mahl and other projects being undertaken by CSAIL will also cement the close and brotherly relations between Government of PRC and GOP.

Salient Features


General

• Project Company : Mahl Power Company (Pvt.) Ltd. (MPCL)
• Location : In AJK at about 5 km upstream of confluence of Mahl River with Jehlum River
• River : Jhelum River

Technical

• Capacity : 640 MW
• Energy : 2,934 GWh
• Project Type : Run-of-River
• PPA Term : 30 Years from COD
• Gross head : 59m
• Plant Factor : 52.33%
• Dam type : Roller-compacted concrete gravity dam
• Design discharge : 1,305 m3/s
• Annual utilization hours : 4,584
• Number of units : 3 Units of 213.33 MW each (Approx.)
 
100 MW SOLAR PV HYBRID PROJECT

Introduction

The 100 MW Solar PV Grid Hybrid Power Project is located in Jhimpir, District Thatta, Province of Sindh, south Pakistan, which is 90km west of Karachi city and 80km north of the coast of Arabian Sea. The project is being developed at the existing site of 3x50 MW Wind Power Projects of Three Gorges First, Second and Third at Jhimpir, Sindh.

Salient Features

General

• Project Company : To be established
• Location : Jhimpir, District Thatta, Sindh
• Type : Solar Power


Technical

• Total installed capacity : 100 MW
• Land required : 500 acres
• Total number of Solar PV modules : 3,92,160 (to be installed)
• Project Term : 20 Years (expected)



Key Milestones


• Issuance of LOI : Jun 21, 2017
• Submission of Feasibility Study to AEDB : Apr 24, 2018
• Tariff & Generation License by NEPRA : Within 5 months of approval of Feasibility Study
 
Govt approves Rs 2,791 mln for power projects under PSDP in FY-2019-20

govt-approves-rs-2-791-mln-for-power-projects-under-psdp-in-fy-2019-20-1593609024-5413.jpg

https://nation.com.pk/NewsSource/app
APP
July 01, 2020

The government has released an amount of Rs 2,790.913 million for various power projects under annual Public Sector Development Programme (PSDP) for fiscal year 2019-20.

According to the data of Planning Commission, an amount of Rs 35,156.212 million was allocated for various power sector projects in the fiscal year 2019-20.

A sum of Rs 809 million has been released for provision of electricity to Dhabeji (SEZ) Sindh, Rs 125 million for supply of power to Rashakai Economic Zone KPK, Rs 75 million for supply of power to Hattar Special Economic Zone KPK, Rs 180 million for construction of 132 KV Grid station in Kapoto Areas District Kalat, Rs 366.200 million for interconnection of isolated Makran/Gwadar Network at Basima via Nag G/Station from Panjgoor Grid Station, Rs 550 million for construction of 132 -KV Grid Station at Isplinji District Mastung and Rs 113 million for electrification of village Dera Bughti.

Similarly, an amount of Rs 275.227 million has been released for construction of 132 KV Grid Station at Deep Sea Port Gwadar and Rs 283.810 million for construction of 132 KV Grid Station at Dadar.
 
2.8 Billion Rupees ,WOW priority wise very good move
 
Night View - 969 MW Neelum Jhelum hydropower project, operation Since 2018.

Photo Credits: Khawar Jamil Rizvi

 
Grid stations in tribal districts to be upgraded

PESHAWAR: A mega project has been launched to improve power supply system in merged tribal districts and upgrade the region’s 66KV grid stations to 132KV ones, Chief Minister Mahmood Khan was told on Friday.

Officials told the chief minister in a meeting that work was in progress on a number of schemes, including provision of express power lines to district headquarters hospitals of merged tribal areas and solarisation of mosques, schools and healthcare facilities.

They said those projects would address electricity issues and ensure people’s development. The participants reviewed progress on the energy and power department’s projects being executed under the Accelerated Implementation Programme (AIP) of merged tribal areas.

Officials said the upgradation of Razmak and Wana grid stations had already been completed, while work was under way on the upgradation of Kalaya grid station in Orkzai tribal district, Alizai grid station in Kurram tribal district, Sadda grid station in Kurram tribal district and Ghalju grid station in Orakzai tribal district.

They said those 66KV grid stations were being upgraded.

Officials said the utilisation of funds against releases for these projects has been cent percent.

They said another project had been approved for the provision of 25 feeders to North Wazirstan, South Wazirstan, FR Bannu, FR Lakki, FR Tank and FR DI Khan, while work had begun on six of them.

Officials said solarisation of around 300 mosques in merged tribal areas had been completed, while the solarisation of 800 more mosques in the region had been proposed.

They briefed participants about action on the announcements made by the prime minister and chief minister during visit to tribal districts.

The chief minister expressed satisfaction with progress on the energy and power department’s projects and asked the relevant authorities to take necessary measures to complete projects within stipulated time to benefit the people of merged areas.

He said the completion of projects on time was the government’s top most priority and he won’t tolerate delay in the projects’ completion.

Published in Dawn, July 4th, 2020
 
Nuclear Power Plants ........

Big Update:

C-1: 142 days of continuous operation and continue
C-2: 360 days of continuous operation and continue, could even go beyond 400 before next planned refueling.
C-3: 160 days of continuous operation and continue
C-4: 366 days of continuous operation, to be shut down for Refueling on 07th july.


Lots of records. Most employees specially of plant operation have not gotten any leave since Covid-19, but still we have ot been given any benefit other than our salaries.
 
Back
Top Bottom