cos of corona very less spending
That’s way too long. They need to figure out ways to work fast.Completion Date 9 Years after commencement
Hey joker wait.. don't go to end..No financial closure ,we needed closed to 8 Billion US$ where is the money ? Its like Musharaf started Neelum Jhelum like that with 80 Billion estimate ending up 500 Billion Rs . What a joke and jokers running the country
spare him poor guy has no idea what he is talking about pre corona estimate was 3/4 Trillion rupees short fall
thank you for pointing out the incompetence of PPPP and PMLN govt who couldn't put aside 30-40b from PSDP..No financial closure ,we needed closed to 8 Billion US$ where is the money ? Its like Musharaf started Neelum Jhelum like that with 80 Billion estimate ending up 500 Billion Rs . What a joke and jokers running the country
spare him poor guy has no idea what he is talking about pre corona estimate was 3/4 Trillion rupees short fall
yes because of the 80% land acquired, 60% was govt land transfer..private land acquiring was stalled..this is open knowledge easily available in google.comNothing will happen. Locals will collect money fourth time for their land. PMLN claimed they acquired 80% of the land with 100 billion rupees, this government is again demanding 75 billion rupees more from poor nation for remaining 20% of land??
Are you living under a rock?? this year budget deficit will be more than 1000 billion rupees.
https://www.thenews.com.pk/print/64...kistan-s-fiscal-deficit-at-9-5-10pc-in-fy2020
https://nation.com.pk/29-Apr-2020/budget-deficit-to-swell-to-9-6pc-of-gdp-due-to-lockdown-situation
local funding for most of the part..First time after 1960 we are building dams at such massive scale.... I wonder where is the funding coming from
Diamer-Basha Dam: Over 14,000 acre land transferred to Wapdathank you for pointing out the incompetence of PPPP and PMLN govt who couldn't put aside 30-40b from PSDP..
if you are going to wait for 100% foreign financial closure than keep waiting..in 2400 AD you will still be waiting....
please learn to googleDiamer-Basha Dam: Over 14,000 acre land transferred to Wapda
This was done before April 2018
Ahsan Iqbal
@betterpakistan
·
Jul 7, 2018
Diamer Bhasha dam land acquisition completed with over Rs 100 billion in last two years by our govt. Earlier, no one had even acquired land.
please learn to google
LAND ACQUISITION
GBA 7,936 Acres
- Land Acquisition process started in 2010 and details are as under:-
- Total Land to be acquired = 37,419 Acres
- Private Land being purchased = 18,357 Acres
- Govt. Land to be transferred (free of cost) = 19,062 Acres
- Private Land Acquired = 8,098 Acres
KPK 162 Acres
http://www.wapda.gov.pk/index.php/projects/hydro-power/ready-for-construction/diamer-basha-dam/item/370-land-acquisition
- Govt. Land transferred to DBDP (free of cost) = 17,214 Acres
- Funds to the tune of Rs. 31,063.000 million have been released for payment of Compensation to affectees in Gilgit-Baltistan against the ADP allocations. Acquisition of remaining private land is actively under consideration of GBA.
- Rs.325.000 million has been released to D.C. Kohistan for land acquisition of Khyber Pakhtunkhwa area for Contractor’s Camp.
- One Window Compensation Cell has been established by Deputy Commissioner, Diamer.
On 20 August 2013- Finance Minister of Pakistan, Ishaq Dar claimed to have convinced the World Bank and the Aga Khan Development Network to finance the Diamer-Bhasha Project without the requirement of NOC from India. He also said that the Asian Development Bank, Aga Khan Rural Support Programme and Aga Khan Foundation had agreed to become lead finance manager for the project.[1][15]
On 27 August 2013- Pakistan's Finance Minister, Ishaq Dar said that work would start on both Dasu and Diamer-Bhasha Dams simultaneously.[16] He also said that Diamer-Bhasha project would take 10–12 years to complete.[17]
On 7 November 2013- the Chairman of Water and Power Development Authority Syed Raghib Abbas Shah claimed that his department has received 17,000 acres of land at the cost of PKR 5.5 billion from Government of [[ Gilgit-Baltistan]] and the Ismaili Community for the construction of the project.[18][19][20]
Former Prime Minister Nawaz Sharif on December 5, 2016 approved, in principle, the financing plan for the Diamer-Bhasha dam and ordered the secretary of water and power to start physical work on the dam before the end of 2017.[21]
On 14 November 2017- Pakistan dropped its bid [22] to have the dam financed under the China-Pakistan Economic Corridor framework as China placed strict conditions including on the ownership of the project. China had projected the cost of the dam to be $14 billion and to secure its investment China wanted Pakistan to pledge another operational dam to it.
5 saal ma tu in sa start na hua...mostly projects musharaf ka zamany na start hua...ppp r n league tu bus delay krtay gy.chahy wo neelum ho,nandipur ho etcOn 20 August 2013- Finance Minister of Pakistan, Ishaq Dar claimed to have convinced the World Bank and the Aga Khan Development Network to finance the Diamer-Bhasha Project without the requirement of NOC from India. He also said that the Asian Development Bank, Aga Khan Rural Support Programme and Aga Khan Foundation had agreed to become lead finance manager for the project.[1][15]
On 27 August 2013- Pakistan's Finance Minister, Ishaq Dar said that work would start on both Dasu and Diamer-Bhasha Dams simultaneously.[16] He also said that Diamer-Bhasha project would take 10–12 years to complete.[17]
On 7 November 2013- the Chairman of Water and Power Development Authority Syed Raghib Abbas Shah claimed that his department has received 17,000 acres of land at the cost of PKR 5.5 billion from Government of [[ Gilgit-Baltistan]] and the Ismaili Community for the construction of the project.[18][19][20]
Former Prime Minister Nawaz Sharif on December 5, 2016 approved, in principle, the financing plan for the Diamer-Bhasha dam and ordered the secretary of water and power to start physical work on the dam before the end of 2017.[21]
On 14 November 2017- Pakistan dropped its bid [22] to have the dam financed under the China-Pakistan Economic Corridor framework as China placed strict conditions including on the ownership of the project. China had projected the cost of the dam to be $14 billion and to secure its investment China wanted Pakistan to pledge another operational dam to it.