Apparently you didn't read the links you shared
//
The PPP government’s failure to get the project completed within its tenure was excessively highlighted by the current ruling PML-N prior to general elections, and apparently reaped the benefits in the form of complete wiping out of the PPP from Punjab.
The project was started in January 2008 at a cost of Rs23 billion. The contract was given to a Chinese firm, which was supposed to complete the work by April 2011.
However, due to unexplained reasons, the then Dr Babar Awan-led law ministry refused to provide legal cover required to import its machinery.
In reaction, the Chinese firm canceled the contract. Despite repeated attempts, Dr Awan wasn’t available to comment what made his former ministry to play the role of a spoiler in this project as described by the judicial commission.
The PML-N soon after coming into power re-initiated talks with the Chinese firm and made it agree to complete its pending work, but the cost was increased to Rs57 billion. As bad luck would have it, the Nandipur power project hasn’t brought good news for the PML(N) government either.
//
PMLN's only fault is that they inaugurated this power plant too soon.
//
Prime Minister Sharif inaugurated the first 95MW plant of the controversial Nandipur Power Project on May 31. The project had been stalled under the PPP government amid allegations of graft, declared an “unforgivable sin” by the prime minister as the plant and related machinery remained stranded at the Karachi port for more than five years.
The project cost more than doubled to Rs57 billion (instead of Rs23 billion) and the nation suffered a loss of Rs165 billion, according to Punjab Chief Minister Shahbaz Sharif, who spearheaded the project’s revival.
The project will be able to generate 425MW on furnace oil, which can be upgraded to 525MW if natural gas is used as fuel.
However, the plant will take another five months or so to achieve commercial operation status.
//
IK and PTI isn't wasting money they are investing money for the cause of Naya Pakistan. If you know anything about current time than you should search the change in KPK and also name at least one corruption scandal of IK. Give me name of any corruption did by IK and PTI in KPK?
What major power projects have gone live in KPK since PTI took charge? IK and Khattak are too busy trying to grab power in other parts of the country.