What's new

Pakistan's Energy & Water - News and Updates

A stark report, with dire warnings. Is anybody listening?

Powerless in Pakistan | Foreign Policy

THE SOUTH ASIA CHANNEL
Powerless in Pakistan
An unending energy crisis could soon bring catastrophic consequences. Here’s what needs to be done before it’s too late.

BY MICHAEL KUGELMAN JUNE 30, 2015

Last week, Pakistan was hit by a heat wave of highly tragic proportions.

The country has suffered through deadly hot spells in the past, but the lethality of this latest one was astounding. According to Pakistani officials, high temperatures killed more than 1,200 people — most of them in Karachi — over a one-week period. The true figure could be much higher, given the likelihood of unreported deaths.

In effect, this heat wave killed more than twice as many people in a matter of days as terrorism has over the entire year (as of late June, about 530 Pakistani civilians had died in terrorist attacks in 2015).

This crisis was exacerbated by rampant power outages. Many households had little electricity to operate fans or air conditioning units; in Karachi, some complained of having no power for more than 12 hours per day. While the rich ran emergency generators, the less fortunate faced stifling conditions that hastened heatstroke and, often enough, death. One woman in Karachi became sick and later died after suffering in an electricity-deprived home that her son described as “like a baking oven.” Power cuts even denied dignity to those killed by the heat wave. CNN’s Saima Mohsin reported that one charity-run morgue had no electricity to keep bodies cool, resulting in an overpowering “stench of death.”

Sadly, such energy woes aren’t surprising.

Deep and Destabilizing

Pakistan has been convulsed by power outages for years. Electricity deficits on any given day may range from 4,500 to 5,000 megawatts (MW), though they’ve sometimes soared to 8,500 MW — more than 40 percent of national demand. These figures are somewhat comparable to those of India (which has experienced shortfalls between 3,000 and 7,500 MW over the last year or so). Many other countries in the developing world, particularly in Africa, also experience power shortfalls of varying levels. Developed countries experience deficits less frequently, though they sometimes face localized modest shortages (for example, in February 2011, power plant breakdowns caused deficits in Texas).

Pakistan’s supply shortages, however, merely represent the tip of an immense iceberg.

As I argue in Pakistan’s Interminable Energy Crisis, a new Wilson Center report, Pakistan’s energy problems are rooted more in shortages of governance than of supply. The energy sector suffers from transmission and distribution (T&D) losses that have exceeded 30 percent, as well as from several billion dollars of debt. The losses are caused by bad equipment, poor maintenance, and energy theft. The debt — often described as “circular” in nature — is a consequence of cash flow problems. Energy generators, distributors, and transmitters lack funds. This is due in part to a flawed pricing policy: The Pakistani government charges a pittance for energy, and yet few customers pay their bills. As a result, revenue is scarce, and the sector literally cannot afford to provide energy.

Pakistan’s energy crisis has troubling implications for its fragile economy and volatile security situation. In recent years, power shortages have cost the country up to 4 percent of GDP. Hundreds of factories (including many in the industrial hub city of Faisalabad alone) have been forced to close. Some Western companies, citing electricity deficits, have suspended operations in Pakistan. In January, the Moody’s ratings group warned that energy shortages will damage Pakistan’s credit worthiness.

Meanwhile, militants are happy to exploit Pakistan’s energy insecurity. Over the last four years, separatists in the insurgency-riven province of Balochistan have targeted more than 100 gas lines. Back in April 2013, the Pakistani Taliban blew up the largest power station in Khyber-Pakhtunkhwa province. Half of Peshawar, the provincial capital with a population nearly as large as Los Angeles, lost power. And just last week, the Pakistani Taliban tapped into widespread anger at Karachi’s main electricity utility, K-Electric, by threatening to attack the facility if it did not restore power.

Wide expanses of Pakistan’s population are affected by the energy crisis. Shortages prevent people from working, cooking, and receiving proper medical care (in some hospitals, services have been curtailed). Not surprisingly, public opinion polls in Pakistan identify electricity shortages as one of the country’s top problems.

In sum, the energy crisis threatens Pakistan’s economy and its precarious security situation, while also deleteriously affecting the lives of everyday residents across the board. Something needs to be done, and fast.

Sustainable Solutions, Not Short-Term Fixes

Pakistan’s Interminable Energy Crisis offers nearly 20 recommendations to ease the crisis in a meaningful and lasting way. It calls above all for a new way of thinking about energy — one that emphasizes more judicious use of existing resources. This means aggressively reducing T&D losses; better enforcing laws against energy theft; developing robust maintenance regimes to ensure that energy infrastructure does not fall into disrepair; and establishing incentives for consumers to use less energy. Achieving these objectives would drastically enhance energy security. Our report estimates that Pakistan’s energy savings potential is about 2,250 MW — roughly half of its total power shortfall.

We also urge officials to pursue a more affordable energy mix. This will require less focus on expensive imports and more focus on indigenous reserves. Pakistan should embrace domestic coal, though within reason; technological and infrastructural constraints preclude heavy exploitation. It should pursue indigenous natural gas alternatives such as tight and shale gas; current reserves are estimated to be quadruple those of conventional natural gas. Pakistan should take advantage of falling solar and wind power costs to increase the proportion of renewables in its energy mix. It can make its mix even greener by adapting other cleaner fuels, such as coal briquettes — which are cleaner than ordinary coal when burned.

Additionally, we recommend more effective energy market policies. Pakistan’s government should scale back its involvement in the energy sector and encourage privatization — but not necessarily full-scale privatization. While electricity generation companies should be fully privatized, it may be prudent for distribution companies — which tend to be larger and employ more people than generation companies — to be restructured through the use of franchising, which transfers operational responsibilities to private actors while the government maintains ownership over assets. Pakistan should also aim to attract a more geographically diverse set of foreign investors. Its aggressive courtship of Chinese companies has made some energy investors from other countries fear the lack of a level playing field.

Finally, we call for institutional reform: Pakistan should bring more coordination and order to a dysfunctional and chaotic energy sector. This means establishing a new energy ministry with overarching responsibility, and with full access to top policy levels; streamlining institutional decision-making processes so that policies no longer need so many approvals (more than 15 government entities are currently involved in energy policy); and integrating energy subsector plans and policies to support national goals. For Pakistan to ease its energy crisis, it needs more effective energy policies — but energy policies can only be as effective as the institutions that shape them.

Costs of Inaction

These are admittedly ambitious proposals, and Pakistan’s risk-averse politicians may wish to have nothing to do with them. That, however, would be a big mistake. Because as bad as things are now, Pakistan’s Interminable Energy Crisis warns, they could soon get much worse.

Pakistan is in the midst of rapid urbanization — a major societal shift that could worsen the effects of energy problems in the years ahead. Demand for electricity is particularly high in cities, because urban industries and homes tend to be more dependent than those in the hinterland on grid-connected energy sources. With droves of Pakistanis entering cities and becoming dependent on grids, supply pressures will deepen exponentially.

And with demand for energy rising dramatically in the coming years, Pakistan could face unprecedented shortages.

Our report concludes that during a period stretching from 2014 into 2015, peak demand was 20,800 MW. This figure is expected to rise to nearly 32,000 MW by 2019. In effect, in just four years, demand could exceed, by nearly 10,000 MW, Pakistan’s current installed capacity of 23,000 MW. To address this gap, Pakistan may need to install as much electrical capacity in the current decade as it did over the last 60 years.

Ultimately, if Pakistan does not move with alacrity to address its energy woes, the challenges that the crisis presents today will seem tame compared to what could be in store in the years ahead.

This means, among other things, that when heat waves strike Pakistan in the future, power outages could be even more lengthy and widespread than they are today.

And, tragically, many people — perhaps even more than the staggering 1,200-in-a-week that perished this time around — would likely die as a result.
 
. .
Delays ,extended deadlines , corruption , probes and commissions . These are the only developments we get in the power sector these days . So far the government performance has been abysmal in solving the energy crisis.
List of debacles

1. Nandipur power project Scam
Nandipur power project: NAB should take action: Shahbaz | Business Recorder

2. Neelum Jhelum delayed for one year .
More hurdles emerge for Neelum-Jhelum hydropower project

3. Tarbela 4 Extension delayed till 2018
Tarbela fourth extension: Project faces delay as only 17% of funds spent so far - The Express Tribune

4 . Dasu Dam also delayed
Dasu hydropower project: Work delayed as issues remain unresolved - The Express Tribune

5. LNG qatar gas details still not worked out .Rumors of heavy lobbying and infighting of PSO ,Sui northern on supply.Corruption in terminal.
NAB probing LNG terminal contract, admits ETPL chief - The Express Tribune


6. Munda Dam ( Critical for stopping floods in KPK) Scrapped .
Plans for building dams scuppered by lack of will - The Express Tribune

Furthermore , work on Bhasha Dam hasn't even started yet . No progress on Bunji dam either. Coal based thar and sahiwal projects are going to be expensive as they will basically be workings as IPPs. Wind and solar power plants seem as to be a positive step , but they wont be enough .

.Hydel projects: government criticised for showing lack of interest | Business Recorder
 
.
France to provide over €41m to Pakistan for rehabilitation of Warsak Dam

France will provide over forty-one million Euros to Pakistan for rehabilitation of Warsak Dam hydropower plant.

An agreement to this effect was signed between the two countries in Peshawar on Tuesday.

The project is aimed at rehabilitating the 243 MW existing Warsak Dam and hydropower plant built in the 1960s on Kabul River, generating up to 1100 GWH per year.
 
.
..............................
3500 MW WIND ENERGY TO BE ADDED TO NATIONAL GRID BY 2018


wind-power-600.jpg


ISLAMABAD: The Alternate Energy Development Board (AEDB) has embarked upon an ambitious plan to enhance the energy mix upto 20-25 per cent by adding 3000-3500 megawatt wind-based electricity to the national grid system by 2018.

"Out of this, as many as 1396 megawatt wind-based electricity will include in the system by 2017 as the AEDB would complete several projects initiated for alternate power generation," Chief Executive Officer (CEO), Amjad A. Awan told APP here.

Awan said that currently the wind projects having 255.4 megawatt power generation capacity are operational across the country including FFC Energy (49.5 MW) Jhampir, ZorluEnerji Pakistan (56.4 MW) Jhampir, Three Gorges First Wind Farm Pakistan (49.5 MW) Jhampir, Foundation Wind Energy - II (50 MW) Gharo and Foundation Wind Energy I (50 MW) Gharo.

He said that 28 ongoing wind projects of 1396.4 capacity would be completed by 2017, which would play a major role in overcoming the energy crisis on which the government is focusing.

He said out of these, 9 projects (477 MW) have achieved financial close and are under construction. These projects include Sapphire Wind Power Company (50 MW), Yunus Energy (50 MW), Metro Power Company (50 MW) Jhampir, Tapal Wind Energy (30 MW) Jhampir, Gul Wind Energy (50 MW) Jhampir, United Energy Pakistan (99 MW) Jhampir, Hydro China Dawood Power (50 MW) Gharo, Master Wind Energy (50 MW) Jhampir and Tenaga Generasi (50 MW) Gharo.

Fourteen wind power projects with a cumulative capacity of 664 MW are at different stages of project development and are expected to be completed by 2017-2018.

He said that there has been strategies that favour that one percent of energy should come through alternate sector, however we aim to rise it up to 20-25 percent by 2018.

He said that power tariff for wind power projects has been reduced to 10.4 cents which indicates that this could prove a promising sector for future investments.

He was of the view that Pakistan was having huge wind-power generation potential and if exploited properly, it could become a very lucrative and feasible source of alternate energy.

"Pakistan naturally is gifted in alternate energy resources and this has been identified by mapping assessment of wind, solar and biomass in the country through ESMAP's (World Bank) assistance.

He said that although the wind potential has been evaluated at a huge scale, however, as far as our studies and surveys are concerned, we have specifically identified the wind corridors having power generation potential of 30,000 megawatt.

He said that the AEDB has identified the high-potential regions including in Southern Sindh, Balochistan and Punjab where electricity generation through wind has promising potential.

Awan said that some of the wind potential areas have also solar intensity, so in such regions both wind and solar energy could be generated simultaneously and this may also be very attractive for the investors.

He said that there has been good responses from the investors to invest in this particular field of energy generation and observed that when the investors are given confidence over the sustainability of the projects, they willingly come to invest.

The CEO said that historically Pakistan has been leading energy sector in the region as it has been pioneering to produced through various sources including coal, gas, bio-gas wind and solar. We were the first to set up regulatory authority and initiated power generation through Independent Power Producers (IPPs).



Copyright APP (Associated Press of Pakistan), 2015...................................
 
. .
Power capacity
..............................
Tarbela 4th extension: Power outages to fall after project completion

It will produce $300m worth of electricity during 2017 high-flow season.

LAHORE: Pakistan Water and Power Development Authority (Wapda) Chairman Zafar Mahmood has called for stepping up construction work on the 1,410-megawatt Tarbela 4th Extension Hydropower Project to complete it by June 2017 in line with the accelerated programme designed to execute the project ahead of schedule.

Expressing his views during a visit to the project site on Tuesday, Mahmood said the extension scheme was of immense importance for overcoming electricity load-shedding in the country with the addition of low-cost hydroelectric power to the national grid.

He was of the view that timely completion of the project would enable Wapda to fully utilise the high water-flow season of 2017 and therefore every effort should be made to achieve the target by removing the bottlenecks.

Mahmood asked project authorities, consultants and contractors to adhere to the timelines of the accelerated programme in addition to ensuring the stipulated construction standards. He inspected ongoing work on the power house during the visit.

Earlier, Tarbela Dam General Manager Iqbal Masood Siddiqui briefed the Wapda chairman about progress on the project, issues being faced by the project authorities and remedial measures for on-time completion of work.

Siddiqui pointed out that early completion of the project in line with the prime minister’s directives would help Wapda generate additional electricity during the 2017 high-flow season amounting to $300 million.

The Tarbela 4th Extension Hydropower Project will increase generation capacity of the Tarbela power station from 3,478MW to 4,888MW after the installation of three units – of 470MW capacity each – on tunnel four of the Tarbela Dam.

The World Bank is providing $840 million for the project, which will produce about 3.84 billion units of low-cost electricity per annum. Annual benefits of the project have been estimated at about Rs30.7 billion and it will pay back its cost in just three years.

........
 
.
Kuwait to invest in solar power projects in Pakistan

QUETTA: A memorandum of Understanding has been signed between Balochistan government and a Kuwaiti Investor Company "Ener Tech" in Quetta.

Provincial Energy Secretary Khaleeq Nazeer Kyani and Chief Executive of the Company Abdullah Almatari signed the memorandum, Radio Pakistan reported on Thursday.

The Ener Tech will install from 50 MWs to 500 MWs solar power generation plants under a phase wise program.

Meanwhile, a delegation of Ener Tech led by its Chief Executive Abdullah Almatari called on the Chief Minister Nawab Sanaullah Khan Zehri in Quetta.

During the meeting, the two sides discussed matters of bilateral interest. Talking on the occasion, Nawab Sanaullah Khan Zehri said that the government wants promotion of foreign investment in various sectors including Solar Energy sector and for this purpose, a comprehensive policy has been chalked out to provide maximum facilities to foreign investors.

Ener Tech chief executive, Abdullah Almatari said that the there are vast prospects of making investment in energy, Live stocks and various sectors in Balochistan and Ener Tech wants t make investment in these sectors.

http://www.thenews.com.pk/latest/130103-Kuwait-invest-solar-power-projects-Pakistan
 
. .
Delays ,extended deadlines , corruption , probes and commissions . These are the only developments we get in the power sector these days . So far the government performance has been abysmal in solving the energy crisis.
List of debacles

1. Nandipur power project Scam
Nandipur power project: NAB should take action: Shahbaz | Business Recorder

2. Neelum Jhelum delayed for one year .
More hurdles emerge for Neelum-Jhelum hydropower project

3. Tarbela 4 Extension delayed till 2018
Tarbela fourth extension: Project faces delay as only 17% of funds spent so far - The Express Tribune

4 . Dasu Dam also delayed
Dasu hydropower project: Work delayed as issues remain unresolved - The Express Tribune

5. LNG qatar gas details still not worked out .Rumors of heavy lobbying and infighting of PSO ,Sui northern on supply.Corruption in terminal.
NAB probing LNG terminal contract, admits ETPL chief - The Express Tribune


6. Munda Dam ( Critical for stopping floods in KPK) Scrapped .
Plans for building dams scuppered by lack of will - The Express Tribune

Furthermore , work on Bhasha Dam hasn't even started yet . No progress on Bunji dam either. Coal based thar and sahiwal projects are going to be expensive as they will basically be workings as IPPs. Wind and solar power plants seem as to be a positive step , but they wont be enough .

.Hydel projects: government criticised for showing lack of interest | Business Recorder
thanks for the work..
unfortunate thing i sthat both the tarbela dam and NJ work was carried on bY PPPP givt which was suppose to be more corrupt
 
.
Pipe Dreams. .......


Pakistani gas company set to emerge as key player on world energy map

By Zafar Bhutta

Published: August 15, 2016



The existing infrastructure in Pakistan lacks the capacity to transport large volumes of gas from the southern to northern regions of the country. PHOTO: FILE

ISLAMABAD: Inter State Gas Systems (ISGS), a company established by the government to work on gas import projects, is striving to secure energy resources to make Pakistan self-sufficient and it is expected to emerge as a key player on the world’s energy map after regional pipeline projects are executed.

Pakistan is eyeing gas imports from countries holding vast deposits and has entered into some key agreements with Iran and Turkmenistan to meet its energy security plan.

Pakistan’s $2 billion LNG pipeline project hits a snag

Iran holds the world’s second biggest natural gas reserves. In December 2012, its proven reserves stood at 1,187 trillion cubic feet as most of them have remained untapped because of international sanctions and delay in field development.

Turkmenistan, on the other hand, holds the world’s fourth largest natural gas reserves with proven deposits standing at 353.1 trillion cubic feet at the end of 2012.

“We have signed all agreements with these countries and financial close of the Tapi (Turkmenistan-Afghanistan-Pakistan-India) pipeline will be achieved by the end of this year,” ISGS Managing Director Mobin Saulat told The Express Tribune.

“Turkmenistan has huge gas deposits and this project will help meet the energy security plan of Pakistan.”

In an effort to bridge the gap between demand and supply of gas, the Pakistan government is pressing ahead with scores of projects including import of liquefied natural gas (LNG), Iran-Pakistan (IP) gas pipeline and Tapi gas pipeline.

Karachi to Lahore pipeline: Pakistan, Russia seal $2 billion energy deal

Domestically, the government has embarked on the much-needed infrastructure development by conceiving the North-South pipeline, which will transport gas from the country’s south to the north, and the Gwadar-Nawabshah pipeline. An LNG terminal has already been built which is another strategic project.

With the easing of sanctions on Iran, Pakistan has stepped up efforts to put the pipeline project on a fast track with high-level visits to and from Tehran. Now, both sides have shown their determination to take the project forward with mutual consensus and accord.

They have also agreed to make necessary amendments to the sale and purchase agreement and set a realistic timeframe for the project’s execution.

ISGS, which has been designated by the government, has continued to engage with relevant stakeholders in Iran and is working to restart the stalled negotiations.

Alternative project

Separately, the government has planned Gwadar-Nawabshah pipeline and LNG terminal, describing it as an ‘alternative strategy’ in relation to the IP pipeline. The Gwadar pipeline, which will be laid with Chinese assistance, will later be connected to the IP pipeline as it has the same route and technical specifications.

Pakistan awards $2 billion LNG pipeline contract to sanction-hit Russian firm

China Petroleum Pipeline Bureau, designated by the Chinese government, will implement the project along with provision of funds. From Pakistan, ISGS has been nominated to undertake work on the project.

Its first phase, expected to be completed by December 2017, will see transportation of up to 600 million cubic feet of re-gasified LNG per day, which will be enhanced to 1.5 billion cubic feet per day (bcfd) through additional compression by December 2018.

The project will act as a major catalyst to diversifying port utilisation and is strategic in nature. It has been put on a fast track as studies conducted for the IP project has been put to use. This has saved time and financial resources.

TAPI pipeline

Though beset by time lapses, inordinate delays, and financial and security challenges, the Tapi pipeline is still a major project that will supply 3.2 bcfd of gas to Afghanistan, Pakistan and India.

The decades-old project, lying dormant since the 1990s, received a fresh impetus in August 2015 with the endorsement of Turkmengaz, a state-owned company of Turkmenistan, as the consortium leader.

Since its groundbreaking in December 2015, work has been initiated on the pipeline and the feasibility study, design and route survey have been completed. A Pakistani proposal to develop a rail and road network from Turkmenistan has also been well received.

Obstacles

However, the existing infrastructure in Pakistan lacks the capacity to transport additional large volumes of gas from the southern to northern regions of the country.

Therefore, keeping in view the LNG supplies, the Ministry of Petroleum has planned to lay about 1,100km-long pipeline from Karachi to Lahore under the title North-South Gas Pipeline, which will carry 1.2 bcfd of gas.

This pipeline will be capable of adding Tapi gas at Multan in addition to the LNG supplied from the Karachi terminal. For this project too, ISGS has been nominated as the executing agency in association with a Russian company.

the writer is a staff correspondent

Published in The Express Tribune, August 15th, 2016.
 

Attachments

  • 1471321246358.jpg
    1471321246358.jpg
    63.1 KB · Views: 75
.
Delays ,extended deadlines , corruption , probes and commissions . These are the only developments we get in the power sector these days . So far the government performance has been abysmal in solving the energy crisis.
List of debacles

1. Nandipur power project Scam
Nandipur power project: NAB should take action: Shahbaz | Business Recorder

2. Neelum Jhelum delayed for one year .
More hurdles emerge for Neelum-Jhelum hydropower project

3. Tarbela 4 Extension delayed till 2018
Tarbela fourth extension: Project faces delay as only 17% of funds spent so far - The Express Tribune

4 . Dasu Dam also delayed
Dasu hydropower project: Work delayed as issues remain unresolved - The Express Tribune

5. LNG qatar gas details still not worked out .Rumors of heavy lobbying and infighting of PSO ,Sui northern on supply.Corruption in terminal.
NAB probing LNG terminal contract, admits ETPL chief - The Express Tribune


6. Munda Dam ( Critical for stopping floods in KPK) Scrapped .
Plans for building dams scuppered by lack of will - The Express Tribune

Furthermore , work on Bhasha Dam hasn't even started yet . No progress on Bunji dam either. Coal based thar and sahiwal projects are going to be expensive as they will basically be workings as IPPs. Wind and solar power plants seem as to be a positive step , but they wont be enough .

.Hydel projects: government criticised for showing lack of interest | Business Recorder
so basically apart from recently floating bids fro LNG plants(after wasting 3 years thinking coal vs LNG, saihwal coal and bin qasim coal project (which was finalized in PPPP era), govt has not made much progress, it has not been able to complete work on 4th extension for which 100% financial closure was achieved in PPPP era, NJ which nawaz govt got more loans and financial closure (credit to them) is still delayed even though tunnel boring machines were acquired by previous govt

on GDP growth just a single digit rise even after massive loans and CPEC(credit to them vs Chinese own global agenda push)

while exports dropped to more than 25%


most concerning key projects either scrapped or work not started, Bhasha, Munda and Dasu are critical projects
 
.
so basically apart from recently floating bids fro LNG plants(after wasting 3 years thinking coal vs LNG, saihwal coal and bin qasim coal project (which was finalized in PPPP era), govt has not made much progress, it has not been able to complete work on 4th extension for which 100% financial closure was achieved in PPPP era, NJ which nawaz govt got more loans and financial closure (credit to them) is still delayed even though tunnel boring machines were acquired by previous govt

on GDP growth just a single digit rise even after massive loans and CPEC(credit to them vs Chinese own global agenda push)

while exports dropped to more than 25%


most concerning key projects either scrapped or work not started, Bhasha, Munda and Dasu are critical projects

This post was from a year ago, there is more bad news i am afraid, the government is now clearly set to miss the deadline for elimination of loadshedding before the 2018 elections. What a complete disgrace ! But still there are guys here who still support the pmln.
 
.
This post was from a year ago, there is more bad news i am afraid, the government is now clearly set to miss the deadline for elimination of loadshedding before the 2018 elections. What a complete disgrace ! But still there are guys here who still support the pmln.

There is posiitve "sentiment" in people of pakistan only(i.e majority which is and will be PML N supporters) but facts and figures are contradicting such claims.

had it not been for CPEC the growth would have been worse than PPPP era

I would give credit to current govt for that but one can argue that it was simply part of Chinese global push agenda rather than PML n doing.

inmost of department of economies govt has not done anything special, alot of expensive loan based infrastructure projects that pushed growth is the only positive aspect of current govt. (or may be negative as some argue)

no investment in any strategic dams or any quick short term power problem fixs
any good govt could have fixed power problem in 3-4 years(PML n claimed 2 years)

at the end of the day PPPP era polices were simply extended, on paper it seems much of the ground work for current projects was simply done in last 2 years of PPPP govt when they woke up(wind-thar coal-tarbela extension financing)

and no they are not going to mis deadline, they will simply make sure power is there for 3-4 days and claim load shedding finished, win the election and it will start agian
 
.
Vestas Plans 1000 MW Wind Energy Capacity In Pakistan

Vestas-Wind-Turbine.jpg

Dutch wind energy equipment Vestas Wind Systems has announced plans to set up 1 GW of wind energy capacity in the Punjab province of Pakistan.

Company officials have signed a letter of intent to develop the first phase of the Quaid e Azam Wind Park, which will have an installed capacity of 250 MW. The project will eventually be expanded to 1 GW capacity.

Vestas has announced that it will seek to raise funding worth $2.2 billion to complete the 1 GW wind energy park.

The Quaid e Azam Wind Park is expected to be implemented in the same lines as the Quaid e Azam Solar Power Park, which also envisages an installed capacity of 1 GW.

Total Wind Power Gen. would reach 2000 MW for All Operational and under going Projects by 2018.

Operational: (308.2 MW)


Zorlu Enerji Pakistan - 56.4 MW
FFC Energy - 49.5 MW
Foundation Wind Energy I & II - 100 MW
Three Gorges First Wind Firm - 49.5 MW
Sapphire Wind Power - 52.8 MW

Under Construction: (Most Projects will be completed by 2018)


477 MW might be added by the End of 2016
Metro Wind Power Co. Limited - 50 MW
Yunus Energy Limited - 50 MW
Tenaga Generasi Limited - 49.5 MW
Master Wind Energy Limited - 49.5 MW
Gul Wind Energy Limited - 50 MW
Tapal Wind Energy - 30 MW
Sachal Energy Development - 49.5 MW
UEP Wind Power (Pvt) Limited - 99 MW
Hydro China Dawood Power - 49.5 MW

1213 MW might be added by 2018
Three Gorges Second Wind Firm - 49.5 MW
Three Gorges Third Wind Firm - 49.5 MW
Hawa Energy Pvt. Ltd - 50 MW
China Sunec Energy - 50 MW
Tricon Boston Consulting Corp. A - 50 MW
Tricon Boston Consulting Corp. B - 50 MW
Tricon Boston Consulting Corp. C - 50 MW
Western Energy Pvt Ltd - 50 MW
Hartford Alternative Energy - 50 MW
Zephyr Power - 50 MW
Shaheen Foundation - 50 MW
Trans Atlantic Energy - 50 MW
Norinco International Thatta Power - 50 MW
Artistic Wind Power - 50 MW
Harvey Wind Power - 50 MW
Zulikha Energy - 50 MW
Gul Ahmed Electric - 50 MW
Din Energy Ltd - 50 MW
Act 2 Wind Ltd - 50 MW
Burj Wind Energy - 14 MW
Quaid-e-Azam Wind Park - 250 MW (Will be Increase to 1000 MW in Phases)


Source: https://defence.pk/threads/feasibil...tts-of-wind-power.296265/page-2#ixzz4In8OUmyh
 
.

Pakistan Affairs Latest Posts

Back
Top Bottom