They are doing work on many projects. Some are under construction, while many are in different stages of feasibility studies. Please note it takes many years for hydro projects feasibility to be completed, as they have to perform many tests, such silt, degradation, Environmental impact, Geophysical, Earthquakes impacts, and many more.
Under Construction
Sr. No. Name of Project Name of District Potential (MW) Completion Date
1. Ranolia HPP Kohistan 17 MW March 2015
2. Machai HPP Mardan 2.6 MW March 2015
3. Daral Khwar HPP Swat 36.6 MW December 2015
4. Koto HPP Dir (Lower) 40 MW 2019
5. Jabori HPP Mansehra 10.2 MW 2018
6. Karora (New) HPP Shangla 11.8 MW 2018
7. Matiltan HPP Swat 84 MW 2019
8. Lawi HPP Chitral 69 MW 2019
TOTAL....................... 271.2 MW
Feasibility Studies Completed Stage-2
S.No
Name of Project Capacity (MW)..... Cost (Rs Billion) Status
Target..... Completion
1-- Kari Mushkar HPP
Chitral 446 MW 174.75 Feasibility Study to initiated ...(Completion 2016---2022
2-- Tor Camp Godobar HPP
Chitral 409 MW... 153.37bn
3-- Gabral Kalam HPP
Swat 110 MW..... 41.25Bn
Total--------------- 965 MW--- Rs.369.37 bn
Feasibility Studies Completed Stage-1
S.No Name of Project Location Capacity(MW)
1 Balakot HPP Mansehra 300
2 Naran HPP Mansehra 188
3 Bata Kundi HPP Mansehra 105
4 Barikot Patrak HPP Dir 47
5 Patrak-Shangrail HPP Dir 22
6 Shogo Kach HPP Dir 102
7 Ghor band Khwar HPP Shangla 20.8
8 Nandihar Khwar HPP Battagram 12.3
9 Arkari Gol HPP Chitral 99
10 Mujigram-Shoghor HPP Chitral 64
11 Istaru Booni HPP Chitral 72
12 Ghrait-Swir Lasht HPP Chitral 377
13 Booni-Zaith HPP Chitral 350
14 Jamshill More Lasht HPP Chitral 260
15 Laspur-Murigram HPP Chitral 230
Total....................... 2249 MW