Infrastructure Development in Pakistan

ISLAMABAD: Modernization and upgradation of PTV Headquarters, Islamabad

12647149_992743114144911_3594610161002048395_n.jpg

12552525_992743154144907_2852637965725932037_n.jpg

12647230_992743197478236_2239385026682660408_n.jpg

12573728_992743214144901_3137570473737264097_n.jpg

12552529_992743254144897_6216772733019822172_n.jpg

12512301_992743280811561_4206319281924673309_n.jpg

12644996_992743324144890_9088730892913029184_n.jpg

12651222_992743344144888_793977245179984918_n.jpg
 
. .
Nice.......................................................
 
.
PTV desperately needs new cameras Lol. On a positive note I've been travelling around Lahore the past week and have been really impressed with the infrastructure works undertaken here, from the underpasses along the canal, to the metro buses to the new centre point/kalma chowk. Work on the orange line is also fully underway having been stuck in traffic in shalmi and lakshmi for ages, due to diversions. Even in sabzazar where my uncle lives, the project is going ahead at great speed.
 
. . . . . .
Port Qasim Coal Power Plant

Great Progress:
85% RCC Work complete
87% Machinery ordered.
June 2017: 660 MW
April 2018: 660 MW
Seeing is believing.


12565430_10208632755807335_314270487940780035_n.jpg

12662670_10208632749527178_6782124906039531162_n.jpg

12654431_10208632753327273_9163329453517281118_n.jpg

12642622_10208632753407275_8302680202647147202_n.jpg

12643004_10208632753447276_7844041850482621716_n.jpg

12509356_10208632754047291_3250865225200286384_n.jpg

12654173_10208632754287297_2907344879263895371_n.jpg

12631294_10208632755967339_4379547952946989362_n.jpg
 
. .
Neelum Jhelum Hydropower Project,

To monitor the performance of Neelum Jhelum Hydropower Project, Minister of state for Water & Power Mr. Abid Sher Ali had visited the project site and had detailed briefing. The Project is being constructed by Energy China Co.

70% construction work of dam has been completed.Design of d dam has been modifed 2 avoid any damage of earth quake. Two hydraulic gates out of 3 have been completed. The rest of work of hydraulic gates will b completed in 2 months

1st TBMs Machine would completed its work in September, 2016 Inshallah! 2nd machine which faced lot of incidents of rock bursting & got damage several time would complete its work in January, 2017

Cans have been fabricated in the steel lining of the project. Power House Complex: Excavation=100% concreting 92 %

13 Transformer have been imported&placed on the site.Excavation of vertical serge shaft&concreting has been completed.

It has been decided that monthly performance of the project would b reviewed&the challenges to the project would b addressed on war footing basis.



12662546_523382087830346_4016929839551385359_n.jpg

12651302_523385084496713_9033869439024667441_n.jpg

12631294_523385057830049_731970236696850509_n.jpg

12509353_523441267824428_5141055495511684740_n.jpg

12645100_523440704491151_2195248289519099882_n.jpg

946153_523441524491069_1347641650159268696_n.jpg

12565553_523442614490960_4978478077672803367_n.jpg

12645050_523442631157625_4378196809725891553_n.jpg
 
. . .
..................................
Three-fourths Neelum-Jhelum power plant work completed,

1036059-NeelumJhelumhydropowerx-1454024140-507-640x480.jpg


ISLAMABAD: About 76% work at the Neelum-Jhelum power plant has been completed and its first unit would start supplying 242 megawatt (MW) electricity to the national grid by July 2017, Minister of State for Water and Power Abid Sher Ali said during a visit to the power plant on Thursday.

“By the end of December 2017, the remaining three units, each having the capacity to generate 242 MW, would start supplying electricity to the national grid.”

The Minister said that the project was delayed due to flawed planning of the previous governments. Completion of the project would help overcome power shortage in the country, he added.

Ali said that as per the promise made by PML-N during its election campaign, the power shortage would end by March 2018. He said that despite financial constraints, the present government continued to work on the Neelum-Jhelum project and has arranged finances for hastening completion.

Lt General (R) Muhammad Zubair, Chief Executive Officer of the project, said in a briefing that over Rs189 billion had been spent on the project to date.

“The project would be completed within the given time period,” he assured, adding that speedy work is in progress for laying transmission lines. “50% of the work to upgrade transmission lines had been completed across the country while work on the remaining transmission lines is in progress.”
.....
 
.