They delivered 6 lca in all these years sir
@Imran Khan Normally I dont reply on defence to Pakistani Members, but as you are very few of sane members here around. All I would say:
Check your figure with hard facts
SP9 is not out of works till now, so till SP8 it is 5 Tejas this Financial Year i.e. from March-2017 to March-2018.
SP-1 ... LA-5001 ... 01-Oct-14
SP-2 ... LA-5002 ... 22-Mar-16
SP-3 ... LA-5003 ... 28-Sep-16
Financial Year 2017-18:
SP-4 ... LA-5004 ... 03-Mar-17
SP-6 ... LA-5006 ... 30-Jun-17
SP-7 ... LA-5007 ... 12-Dec-17
SP-5 ... LA-5005 ... 02-Feb-18
SP-8 ... LA-5008 ... 13-Mar-18
SP-9 ...LA-5009 All possibility that the delivery is made before the end of March-2018.
Look out the DELIVERIES FROM DECEMBER-2017 onwards; 03 Tejas delivered and 4th one is on the verge of delivery. Which means 04 Tejas in 04 months.
And you are saying manufacturing speed is slow????
Mark my words from April-2018 to March-2019 they are set to deliver 01 Tejas every month i.e. 12 in Financial Year 2018-19.
And in 2019-2020 they are planning to deliver 16 Tejas.
Is this slow speed???
Because they have not setup a production line as LCA MK1 was... you know the story...
Just cross check the available data.