The development of Gwadar Deep Sea Port as per approved PC-I and Master Plan is to be undertaken in two phases.
Phase-I comprises of:
3 Multipurpose Berths
Length of Berths 602m
4.5 Km long Approach Channel Dredged to 11.5m-12.5m.
Turning Basin 450m dia.
One 100m Service Berth.
Related port infrastructure and port handling equipment & Pilot Boat, Tugs, Survey Vessel etc.
The port is equipped with the essential port handling equipment and other infrastructure required for smooth operations of a modern port. The Port will handle Bulk Carriers of upto 30,000 DWT and Container Vessels of 25,000 DWT. Phase-I was completed by March 2005.
Phase II
This Phase of the Project is planned to be built on BOO/BOT basis at an estimated cost US$. 600 Million and is nearing completion. It will comprise of 9 additional berths as per following details:
4 Container Berths.
1 Bulk Cargo Terminal (to handle 100,000 DWT ships).
1 Grain Terminal.
1 Ro-Ro Terminal.
2 Oil Terminals to handle 200,000 DWT ships.
Phase II of the project involves construction of more berths on BOT basis including two container berths, one bulk cargo terminal, one grain terminal with capacity handling vessels up to 100,000 DWT, one roll on/ roll off terminal, two oil piers for vessels up to 200,000 DWT and future expansion of two container berths. On completion of the project, Gwadar Deep-sea port would be on of the world's most strategically located port in this part of the world.
On successful completion of Phase-I, it is anticipated that the private sector would come forward to invest in the second phase of the Project. It is envisaged that the complete development of such a Mega project will take 8-10 years depending on the active participation of the private sector.
Hope this answers your question.