Energy Projects...Updates

Jagran-II Hydropower Project - 48MW

Work on the project continues. 3.95 Km of tunnel excavation has been completed which includes 2.99 Km of Headrace Tunnel. Besides tunnels, earthwork of Weir flow section has also been completed and being prepared for structural works.

Credits: FWO


1618489808378.png
 
Jagran-II Hydropower Project - 48MW
Work on the project continues. Earthwork of Weir flow section has also been completed and being prepared for structural works,


1618577090876.png




1618577150442.png
 
The integral withstand voltage test of the first generator stator for Karot Hydropower Project has passed.
Three-phase four-branch star connection mode adopted for stator windings. The double-layer strip wave winding performed using an epoxy mica insulation system with class F insulation.
The smoothly completion of this important task laid down a solid foundation for the rotor hoisting of first unit in May 2021.


1618662813236.png






1618662835722.png
 
′′ Carbon emissions from Sahiwal Cole Power Plant is zero ′′

Cool fired power plants operated under Chinese companies in Pakistan are working on zero carbon emissions.

Sahiwal Cole Power Plant has made it very low even zero carbon emissions possible.

The Sahiwal project is involved in green coal-operated power projects with its high performance and carbon emissions that have met world standard. The project is built on the style of Tianjin IGCC power station,

This project uses various devices and technologies for carbon dioxide reduction which is then stored as industrial raw materials


1618663251640.png
 
Jhimpir Wind Turbines, after sunset.
Inter-turbine distance is around 1200 ft (360 m).
🙂


"The Jhimpir Wind Power Plant was developed in Jhimpir, Sindh by Zorlu Energy Pakistan. The total cost of project is $136 million. Completed in 2002, it has a total capacity of 50 MW. This wind Corridor has a 50000 megawatt potential with average wind speeds over 7 meter per second."


1618757028371.png
 
High-pressure cylinder and the intermediate-pressure cylinder of Lot#1 for Jamshoro Thermal Power Plant were successfully hoisted in place.

The milestone laid down a solid foundation for the installation of the steam turbine generator set.

The installation is undertaken by the consortium of Harbin Electric Company Limited & Siemens.

Photo Courtesy: Harbin Electric Company (HEI)



1618872228380.png





1618872255860.png




1618872280587.png
 
Minister for Energy, Mr. Hammad Azhar and Punjab Energy Minister Dr. Akhtar Malik attends MoU ceremony of USD 708 million, 1263 MW PTPL, RLNG based Power Project, located near Trimu Barrage, District Jhang, at Islamabad.


1619267540962.png
 
Mohmand Dam Hydropower Project - 800 MW
Under Construction since September 2019
Gross Storage 1.2 MAF
Annual Energy Production 2,862 GWh
Completion date: 2025



1619356829565.png





1619356856421.png
 
Under Construction Dasu Hydropower Project - 4320MW (First Stage: 2,160MW)

Concrete works at the inlet of Diversion Tunnel B is in progress.

Credits: Engr. Asim


1619359414366.png




1619359437703.png
 
1,263 MW PTPL Power Project achieved Financial Close today. The Power Plant located near Trimmu Barrage, District Jhang is based on re-gasified liquefied natural gas (RLNG) and is so far the largest RLNG based power generation project under Power Generation Policy 2015.

The Financial Closing ceremony was graced by the Honorable Minister for Energy, Mr. Hammad Azhar and Punjab Ministers. Financial Closing documents were signed by Mr. Shah Jahan Mirza, Managing Director PPIB and Mr. Akhtar Hussain Mayo, Chief Executive Officer of PTPL while Chairman PPIB/Secretary Power Division, Mr. Ali Raza Bhutta and other senior officials of Power Division, PPIB and the project company witnessed the proceedings.

The project is being developed in IPP mode through Punjab Thermal Power (Pvt.) Ltd. (PTPL), a private limited company owned by the Government of Punjab through Energy Department. This is the second RLNG based power project developed by Government of Punjab through its own resources, the first being the Bhikki Power Plant, which has already entered full-fledged combined cycle commercial operations and has generated over 9.3 billion units during last year.

PTPL project is being financed through 75 percent commercial debt arranged from local banks which include National Bank of Pakistan, Bank of Punjab, United Bank Limited and Habib Bank Limited while the total cost involved in development of this project is US$. 708 million.

Utilizing state of the art technology, the plant has the design efficiency of 61.16% which is rated amongst highest efficiencies in the world, which would result in fuel-saving of billions of rupees to the national exchequer during 30 years project life period while reducing overall tariff.

Despite delay in Financial Closing and commissioning of project due to COVID-19 implications, the project company adopted proactive approach and started construction of plant by injecting its own equity. Due to dedicated efforts of the Punjab Government coupled with continued support of Federal Government, Power Division and Private Power & Infrastructure Board (PPIB) the plant has reached at advanced stage with over 80% construction works completed. Efforts are being made to bring this project of national importance online by October 2021 on open cycle mode and on combined cycle mode by June 2022.

Upon commissioning of the Project, it will also help in stabilizing and balancing the transmission system to improve uninterrupted supply to Faisalabad and adjacent areas. The Project will generate more than 3000 employment opportunities during construction phase while 2000 during its operations.

Speaking on the occasion, Mr. Hammad Azhar remarked that our energy issues are complex and multifaceted in their own way. Many of our energy woes are attributed to a lack of focus on the part of successive governments to diversify the energy mix by harnessing cheap and indigenous sources of power generation.

As the incumbent government under PM Imran Khan took on this challenge, the matter of generating low-cost electricity, which is both affordable and environmentally-friendly as well as focusing on renewable energy resources like hydel, wind and solar has been the foremost priority. a greater concern. It is this quest for making Pakistan the embodiment of the Quaid’s and Iqbal’s ideals that continue to guide our efforts as we go about performing the fundamental task of turning the country towards progress on different fronts.


1619365264149.png
 
Jamshoro Ultra-Supercritical Thermal Power Plant 2X660MW undertaken by the consortium of Siemens Energy and HEI.
On Apr. 20, 2021, No.1 Cooling Tower for the Project successfully topped out, marking a critical step forward in the on-site construction.


1619461150081.png
 