What's new

Energy Projects...Updates

Bhikki Power Plant ... 1180 MW




21ef9f204936922df4bb99c3a1aa50e4.jpg





6eb677099837345114da6347e8460dc4.jpg
 
. . . .
This is great news !! Tarbela dam will become the 10th largest producer of hydropower in the world after 5th extension.

World Bank approves $390m loan for Tarbela fifth extension

ISLAMABAD: The World Bank has approved a $390 million loan for the Tarbela fifth extension to add an additional generation capacity of 1,410 megawatts, a development that also marks the lender’s first co-financing project with the Asian Infrastructure Investment Bank (AIIB) in South Asia.

For long, the China-based AIIB and World Bank, based in Washington, had been seen as rivals to each other, but the two lending institutions signed an agreement earlier this year to undertake joint projects.

The Tarbela fifth extension will be the duo’s first co-financing project in South Asia.
The AIIB will also extend a $300 million loan for the project, which will be its second project in Pakistan and first in the energy sector. The AIIB may also approve the $300 million this month.


The Board of Directors of World Bank approved the loan to help a sustainable expansion of Pakistan’s electricity generation capacity, according to a handout issued by the local office of the Washington-based lending agency.

The share of World Bank in the total project cost of $826.1 million is 48%. The AIIB will provide $300 million while Water and Power Development Authority and National Transmission and Dispatch Company will arrange the remaining $133.1 million.

The World Bank’s loan is a relatively expensive one with Pakistan due to return the amount in 20 years.

The Tarbela Fifth Extension Hydropower Project will add 1,410MW of low-cost electricity generation during the high-demand summer season. The loan finances the installation of a powerhouse at the existing tunnel five that will enhance the total capacity at Tarbela to 6,298MW. Three units with a capacity of 470MW each would be constructed on tunnel-5, which is on the left bank of Indus River.

The current installed capacity of the 3,478MW Tarbela hydroelectric power stations will increase to 6,298MW after completion of the ongoing fourth extension and the planned fifth extension. The World Bank had earlier given $840 million for the fourth extension.


The government wanted to complete the fourth extension by June 2017, also having 1,410MW capacity, and paid an extra $51 million to contractors and suppliers. However, the government will still miss the deadline and out of three units of Tarbela fourth extension only one unit is expected to be completed by August 14, according to officials involved in project execution. The remaining units may be ready by the end of 2017.

Work on the fifth extension will be completed in three and a half years from the date of inception. The fifth extension is among half a dozen hydroelectric and nuclear power projects with a cumulative generation capacity of 14,700MW, which would be completed between 2018 and 2023.

For the last many years, Pakistan is facing acute power shortages. In the fiscal year 2015-16, the country’s total generation capacity was 18,760MW during the summer and 14,833MW in winters, whereas the demand remained around 22,880MW.

Pakistan’s power needs are increasing at a growth rate of 7% to 8% per annum. Various estimates suggest that the demand will be 96,000MW by 2029-2030 whereas additional generation is too slow to keep pace, according to World Bank project documents.

The Executive Committee of National Economic Council recently approved the fifth extension project at a cost of Rs81 billion on the condition that Indus River System Authority (IRSA) will certify that the expansion would not affect the water flows for irrigation purposes.

The construction of powerhouse on tunnel five would proceed in parallel to the ongoing work on tunnel four in a manner that it would remain operational until the construction of powerhouse on tunnel four is completed and available for water releases for irrigation purposes, said the World Bank. The project also includes the laying of about a 50-kilometre long transmission line for carrying additional generation from Tarbela to the national grid.

Increased supply at competitive prices from tunnel five will support economic growth for all enterprises that use electricity, regardless of size or sector, said Illango Patchamuthu, the World Bank country director for Pakistan. He said that the project will contribute to long term energy security.
 
. . . .
147 MW Patrind Hydro Power Project in Muzaffarabad Azad Kashmir Under Construction
Commission date: April 2017
Installed capacity: 150 MW (200,000 hp)
Owner(s): Water and Power Development Authority (WAPDA)

Update


14462983_953913334736365_3419301629886108475_n.jpg






14445945_953913378069694_557807139909113474_n.jpg





14492600_953913374736361_8098394195502638653_n.jpg






14462783_953913404736358_1026690959794025111_n.jpg
 
.
102 MW Gulpur Hydro Power Project, Kotli, Azad Jammu & Kashmir
Total capacity reservoir: 21,893,000 m3 (17,749 acre·ft)
Opening date: Expected August 2018

Gulpur Hydropower Project is the third independent hydropower project in Pakistan. Korean company has also been awarded other contracts to build hydropower plants in the country on BOOT basis i.e. under construction 150 MW Patrind Hydropower Plant and 100MW Kotli Hydropower Project.

14359202_954814491312916_6428147460803900871_n.jpg





14517368_954814497979582_1557260975495484127_n.jpg






14355608_954814564646242_2294059307369378059_n.jpg





14440900_954814544646244_1463244498237557513_n.jpg





14517564_954814547979577_7239867803526574687_n.jpg
 
. . . . . .
Back
Top Bottom