What's new

Energy Projects...Updates

Matiari-Lahore Transmission Line China State Grid....... Negotiation in Process........15% Completion

Matiari-Faisalabad Transmission Line China State Grid... Negotiation in Process.........15% Completion
 
. .
102 MW Gulpur hydropower plant starts production

Gulpur Hydropower Project has achieved certified commercial operation and has started producing cheap electricity for the national grid, said NESPAK Managing Director Dr Tahir Masood in a press communiqué on Wednesday.

NESPAK, in a joint venture with MWH Inc USA, has provided consultancy services as ‘owner’s engineer’ to Mira Power Limited, a subsidiary of KOSEP South Korea, for the 102MW Gulpur Hydropower Project.

“NESPAK has played a very vital role in the successful completion of Gulpur Hydropower Project, as it provided complete technical support to Mira Power Limited in getting approvals from different government agencies as well as supporting the EPC contractor in resolving complex issues that arose during construction,” said a statement issued by the company.

The successful completion of this project has added another feather in NESPAK’s cap, as the company had recently played a major role in the development and completion of 84MW New Bong Escape Hydropower Project

 
.
Construction work of grid station at Choochang under the component of 132 kV transmission line of Dasu HPP -WAPDA Kohistan, is continued and soon it will be completed


 
.
660kV Matiari Lahore HVDC Transmission line Project will evacuate power North-South resolve one major issue

Scope;4000 MW Evacuate Capacity,
886 KM,
1972 Towers.
Cost: USD 1.658 Billion

Work completed: 85%-
 
.
117036072_2950079388453073_8491673574397824571_o.jpg





117263438_2950079508453061_2614307341330484526_o.jpg
 
. . . . .
Keyal Khwar Hydropower Project

Location

The Project is located on Keyal Khwar Nallah, a right bank tributary of Indus River in Lower Kohistan District of Khyber Pakhtunkhwa situated at a distance of 310 km from Islamabad on Karakaram Highway

Salient Features
  • Gross Head
732 meter

keyal.jpg

  • Installed Capacity
128 MW
  • Annual Energy
418 GWh

Consultants
Keyal Hydropower Consultants (KHC), JV of Lahmeyer Int., NDC and EASE-PAK



Donor Agencies
KfW Germany, European Investment Bank (EIB)

Status:-

  • Detailed Engineering Design completed in December 2011.
  • The Contract for Civil & Hydraulic Steel Works terminated due to non-performance of Civil Works Contractor on 08.12.2017. The Contractor handed over the entire Project to the Employer on 30.01.2018.
  • WAPDA requested M/s KfW for issuance of “No Objection” to proceed with bidding process of the Civil Works Contract.
  • KfW issued No Objection on 09.08.2019 for commencing tendering process of Keyal Khwar HPP by adopting Pre-Qualification procedure instead of Post Qualification, subject to the availability of funds as proposed by WAPDA.
  • As per guidelines of Donor Agency regarding change in bidding criteria, Project Consultants were requested to modify the bidding documents on 27.09.2019.
  • Islamic Development Bank (IsDB) alongwith Coordination Group Partners carried out Energy Sector Technical Dialogue with WAPDA on November 18, 2019.
  • 3rd revised PC-I has been submitted to Chief Engineering Advisor, Federal Flood Commission, MoWR on 13.02.2020.
  • Bidding documents for E&M Works are under preparation.
Physical Progress 9.99%
 
.
KurramTangi Multipurpose Dam project coming along at a staggering pace due to relentless efforts by FWO work force. Once online in 2022 the Dam will see 18 MW of power generation and 41Kms of irrigation canals capable of irrigating 16400 acres of land under stage 1.

On completion of stage 2, the total combined capacity of the Dam will be an astounding 83 MW bringing much needed prosperity for the populace of newly merged North #Waziristan District of KPK.

Courtesy: FWO




 
.
The return of the engineers and managers to Pakistan, which had been delayed because of the Covid-19 pandemic, is expected to provide a boost to the Thar Coal Block-1 Project.

 
. . .

Pakistan Affairs Latest Posts

Back
Top Bottom