What's new

Energy Projects...Updates

NEPRA Approves Increase of 55 Paisa Per Unit in Power Tariff

The National Electric Power Regulatory Authority (NEPRA) has approved an increase of Rs. 0.55 per unit in power tariff, on account of the fuel cost adjustment for April 2019.

The decision was made in a public hearing of a petition put forth by the Central Power Purchasing Agency (CPPA) on behalf of the distribution companies (DISCOs).

The decision will have an impact of around Rs. 5.2 billion on consumers. However, the tariff adjustment will not be applicable to lifeline consumers, who use up to 50 units a month, and to K-Electric consumers.

CPPA’s petition asks for an increase of Rs. 0.5696 per unit in the electricity tariff because of the hike in fuel prices. It maintained that a reference tariff of Rs. 5.2359 per unit was charged to the consumers in April while the actual tariff was much higher, i.e., Rs. 5.8055 per unit. Therefore, it should be allowed to increase the tariff by Rs.0.5696 per unit.

The petition pointed out that the total energy generation in April was recorded at 9,717.38 gigawatt-hours (GWh) at a cost of Rs. 53.63 billion, which is Rs. 5.5190 per unit. The net electricity delivered to the distribution companies was 9,511.79 GWh at the price of Rs. 55.22 billion while the transmission losses accounted for Rs. 0.1080 per unit.

Electricity Production Stats
Data provided to NEPRA shows that the share of hydroelectric power generation stood at 22.94 percent at 2,229.41 GWh in April. During the month, 4.95 percent or 481.05GWh electricity was generated from furnace oil, at a cost of Rs. 12.34 per unit.

No electricity was generated from high-speed diesel in the said month while the power generated from re-gasified liquefied natural gas (RLNG) was recorded as 2,995.81 GWh, i.e., 30.83 percent of the total generation. The calculated cost of RLNG-based electricity was Rs. 9.4 per unit.

The local gas-based plants contributed 1,789 GWh or 18.42 percent to the power generation at a cost of Rs. 6.06 per unit. Coal-based energy production was 1,005.04 GWh or 10.34 percent in April while the cost was Rs. 6.78 per unit. Nuclear power plants’ share was recorded as 745.20 GWh or 7.67 percent in April while the cost stood at Rs. 1.013 per unit.

Bagasse-based electricity contributed 66.43 GWh to the overall electricity generation at a price of Rs. 6.11 per unit. Energy imported from Iran in the said month was 42.43 GWh or 0.44 percent of the total, at a cost of Rs. 11.5709 per unit.

Energy production from wind contributed to 267.44 GWh and its share was 2.75 percent while the share of solar energy in the generation mix was 66.50 GWh or 0.68 percent at no cost
 
Hub Power Plant.

49251289_2248941088655105_275316354385444864_o.jpg


49676612_2248941051988442_8653738568860041216_o.jpg
 
KP Govt expedites work on Sharmai hydro power project ..Dir:
150 MW

June 16, 2019

3435414771560703317.jpg



Khyber Pakhtunkhwa government has expedited work on the construction of Sharmai hydro power project in Upper Dir district.

A spokesman of Pakhtunkhwa Energy Development organization told our Peshawar correspondent, that the project will be completed at a cost of forty-five billion rupees by 2023.

The project also includes construction of seven-kilometer-long tunnel to divert water of Panjkora River for power generation.

The spokesman said on completion, it will generate one hundred and fifty megawatt electricity.
 
Progress Pictures of 1263 MW Punjab Power Plant, Jhang Under Construction. This is the 4th RLNG Power Plant started by Government of Punjab in last tenure along with Balloki, Bhikki & Haveli Bahadur Shah Power Plants..


65316946_2087708241356863_1608171841661173760_n.jpg




65305574_2087708451356842_4013409705593405440_o.jpg


65786490_2087708531356834_3969356440786698240_o.jpg





65667756_2087708638023490_1985117391536783360_o.jpg




65435654_2087708824690138_169411115225186304_o.jpg
 
List of completed projects under CPEC
1.50MW Dawood Wind Farm
2.100MW Jhimpir Wind Farm
3.50MW Sachal Wind Farm
4.2x50MW Wind Farm Phase II of Pakistan
5.300MW Quaid-e-Azam Solar Park in Bahawalpur
6.2x660MW Port Qasim Coal Power Plant
7. 2x660MW Sahiwal Coal Power Plant

66755041_2115902311870789_3285221923524444160_n.jpg



67333514_2115902535204100_3317054627689529344_n.jpg



67582804_2115902415204112_8113074002441797632_n.jpg
 
KARACHI (PR) Reon Energy Limited has announced the commissioning of its latest 12.5 MW captive solar power project at Fauji Cement Company Limited (FCCL) in Jhang Bahtar, Punjab. The proposed move is a key step in commercializing a unit in order to achieve a lower cost of electricity.

Mujtaba Haider Khan, CEO, Reon Energy Limited, said “The 12.5 MWp solar plant shall offset higher energy prices for power from grid and other sources. Cement sector is going through a tough patch, lower prices and demand compression; this initiative should help preserve margins in a tough environment.

I commend the Fauji Cement team for taking a leap towards energy independence; we’re privileged to have played our role.”

The solar plant was said to create 500 jobs during the project duration.
 
Hanzal hydel power project to be launched soon: Jafarullah Khan

July 27, 2019

10328714981564239111.jpg



Deputy Speaker Gilgit-Baltistan Assembly Jafarullah Khan has said development projects costing billions of rupees are being implemented in his constituency in Gilgit.

Talking to media in Gilgit today, he said 20 MW Hanzal hydel power project would be launched soon, which will help end load-shedding in the district.

He said construction work on 16 MW Naltar and 6 MW Kargah hydel power project is also in progress while contract of 3 MW Nomal project would be awarded shortly.
 
Some nice clicks of the amazing Sahiwal coal power plant under CPEC. It was completed and put into operation with high standard and in record 22 months period. The plant started its commercial operation 200 days ahead of the given schedule.

 
1320 MW CPHGC coal power plant's second unit connected to the national grid

China Power #Hub Generation Company’s (CPHGC) 1320 MW coal fired power project under the China-#Pakistan Economic Corridor (#CPEC) is now functioning smoothly as the second unit of the mega project is connected to the national grid.

The project is a joint venture between China Power International Holding (CPIH) and #Hubco Pakistan. The project is worth $2 billion, and will provide nine billion kilowatt-hours of electricity every year.

69266786_2166152056845814_2674815686743687168_n.jpg




68360044_2166151993512487_1541276437535784960_o.jpg




67891147_2163354587125561_4130187096117739520_n.jpg
 
Lucky Electric Power Company

Lucky Electric Power Company is a wholly owned subsidiary of LCL Holdings Limited which is fully owned by Lucky Cement Limited. The Company is in the process of setting up a 660 MW coal fired power plant with super critical technology located in Deh Ghangiaro, Bin Qasim, Karachi.

ahv6qDw.png



hbAfuEe.jpg


Pic-2.jpg


Pic-3.jpg

,

z9rROJR.png
 
China ships equipment for $1.7bln energy project



523523_4375880_Chinese-equipment_akhbar.jpg


BEIJING: A Chinese company has shipped power equipment to Pakistan for the country’s first $1.7 billion worth of transmission project under the China-Pakistan Economic Corridor (CPEC) framework.

Fushun Electric Porcelain Manufacturing Company shipped 30 tons of direct current (DC) 660 kilovolts of Zinc Oxide Lightning Cooler to Pakistan for its grid project from Shen Fu new area.

Wang Youxue, member of the Party Work Committee of the Shen Fu New District of China’s Liaoning province and deputy director of the Management Committee told China Daily News that the Fushun Electric Porcelain Manufacturing Company participated in the project as it was one of the key cooperation projects of the belt and road Initiative.

Youxue said the DC transmission project is also the first landing project for Pakistan to open foreign investment in the field of power transmission and transformation. The total investment of the project is $1.658 billion and it will be officially put into operation in 2021.

Based on the technical advantages of its own ultra high voltage products for many years, Shen Fu New District Fushun Electric Porcelain Manufacturing Company successfully won the bid for the alternating current and DC pillar insulators and metal zinc oxide surge arresters of the project, with a total contract value of more than 57 million yuan. Shen Fu New District has been paying attention to and supporting the transformation and upgrading of traditional enterprises in the new district.

Youxue said Fushun Electric Porcelain Manufacturing Company is actively responding to the belt and road initiative and went abroad. “Shen Fu New District will serve the enterprise and help the rapid development of the enterprise.”

The enterprising spirit of struggle marked a significant progress in the belt and road national grid project of Fushun Electric Porcelain Manufacturing Company.

The Matiari-Lahore high-voltage direct current transmission line project has already secured financing. This is the country’s first private sector transmission project under CPEC and will transmit more than 4,000 megawatts of coal-based electricity from projects in Sindh to the Punjab’s main grid.

Besides the transmission project, the Private Power Infrastructure Board is currently facilitating implementation of power projects having cumulative capacity of 10,934 megawatts under CPEC, which include various hydel and coal-fired projects.

CPEC envisaged capital investment of $60 billion to generate economic activities. Most of the committed investment is targeted at improving generation capacity and transmission capability in the energy sector of Pakistan. Apart from focusing on energy, infrastructure and Gwadar projects, nine special economic zones are being established under CPEC portfolio to revive industrialisation process by foreign and Chinese’s businesses and technology transfers and transformation.
 
Biggest power plants under #China’s Belt and Road Initiative (BRI)

Eight of the ten biggest power projects under China’s ambitious Belt and Road Initiative (BRI) as of 2019 are in Pakistan, within the #China Pakistan Economic Corridor (#CPEC). The combined capacity of the ten biggest BRI power projects is 20.97GW, out of which Pakistan’s share is 9.57GW (45%). Power-technology lists the biggest power projects under the BRI, based on capacity.

The top ten biggest power plants under the Belt and Road Initiative: Ranking the BRI power projects

10. Suki Kinari Hydropower Project, Pakistan

9. Quaid-e-Azam Solar Park, Pakistan

8. Kohala Hydel Project, Pakistan

7. Thar Mine Mouth Oracle Power Plant, Pakistan

6. SSRL Thar SEC Mine Mouth Power Plant, Pakistan

5. CPHGC Power Plant, Pakistan

4. Sahiwal Coal-fired Power Plant, Pakistan

3. Port Qasim Power Project, Pakistan

2. Hassyan Clean Coal Project, UAE

1. Kayan River Cascade Hydropower Project, Indonesia
 
Back
Top Bottom