What's new

Energy Projects...Updates

Karot Hydropower Project | 720 MW
Update 11/2/2018.


Karot.jpg
 
Electrical & Mechanical Equipment Installed at Tarbela 4th Extension hydro power project by German Firm Voith Hydro.

27747378_1811028405608097_8373440382950530223_o.jpg




27798315_1811028818941389_7212840742123694175_o.jpg




27788283_1811028712274733_3674076416076286547_o.jpg




27655370_1413440732116954_7552496402097078680_n.jpg
 
Last edited:
99 MW UEP Jhimpir Wind Farm. Some latest pictures of the Admin Building, Substation, Wind Turbines and Temporary Site Facilities.


27858100_1413491575445203_4947087308907023003_n.jpg



27751933_1413491638778530_2568704319514606188_n.jpg



49.5 MW Hydrochina Dawood Power started operations in April 2017. This project will provide electricity to 100,000 households.


27655344_1413492672111760_1464659159439779818_n.jpg



27867647_1413492715445089_211030200885084050_n.jpg
 
99 MW UEP Jhimpir Wind Farm. Some latest pictures of the Admin Building, Substation, Wind Turbines and Temporary Site Facilities.


Winds of change...not only at Jhimpir Sindh, around Keenjhar lake but many areas around Keti Bandar and Sindh river delta are going through these renewable wind power generation projects.

Good to see this change and more emphasis towards renewable and sustainable energy.
 
Tail-race pond is full and ready for commissioning. Tarbela 4th hydropower .


26910872_1792455980798673_6957992134926875778_o.jpg





27710002_1806560532721551_6562439397164414044_o.jpg



Great moment. 470 MW machine virgin mechanical run carried out successfully. GM (P)T, CE/PD, T-4 deserve big applause...
Tarbela 4th Extension hydropower project..

 
KP Government has produced over 90 MW electricity in different parts of KP since 2013, projects with a capacity of over 2500 MW are initiated, and further 2700 MW projects are under review; images of under construction 10.2 MW Jabori Hydropower project in Mansehra‬ KPK












 
China Electric Power Equipment and Technology Co. is working on MATIARI-LAHORE ±660kV HVDC Transmission project.
The capacity is 4000 MW. Length of transmission line is 878km. Construction period is approximately 27 months.


27858868_1414247272036300_2558508315695106972_n.jpg



27655486_1414247325369628_1612026980718853448_n.jpg


27657165_1591641920888955_5220538082441576770_n.jpg



DVxnmEuX4AANU0g.jpg
 
Last edited:
The CDWP recommended the Evacuation of Power from Suki Kinari, Kohala and Mahl hydropower projects at a total cost of Rs 73.6 billion to Ecnec. The main objective of the project is construction of a 500kV transmission network to provide interconnection facilities for evacuation of power.
 
Steam Turbine at 1230 MW Haveli Bahadur Shah Power Plant has been successfully synchronised with the National Grid.

27973858_1418218788305815_5993398100897440770_n.jpg




28058851_1418218818305812_2803508973503267694_n.jpg




27857819_1418218754972485_7820078048658816468_n.jpg
 
Neelum–Jhelum Hydropower Plant ... 969 MW

Subsequent (stage 2) reservoir filling from El. 990~1002. 1st Tunnel filling to follow soon InshaAllah.


27972435_1419471288180565_7488829065348798341_n.jpg




28059107_1419471391513888_773391184647096574_n.jpg


Balloki Power Plant | 1223 MW

27540334_561528990875377_5429425985778203458_n.jpg


HUBCO Coal Power Plant | 1320 MW

Updates 11/2/2018.

HUb_2.jpg


Hub.jpg
 
Nepra issues licence for Matiari-Lahore line


5a8e21e718925.jpg


Transmission lines are crucial to carry the additional power from the projects under implementation to the final consumer. Unlike these lines, the Matiari line will be the first high voltage direct current line in the country.

ISLAMABAD: The National Electric Power Regulatory Authority (Nepra) on Wednesday granted a 25-year special purpose transmission licence to Pak Matiari-Lahore Transmission Company Ltd (PMLTCPL) — a company owned by three Chinese firms — for the construction of 878-kilometre line.

The special purpose vehicle (SPV) company PMLTCPL will be owned by two Hong Kong-based companies: Zhong Cheng Xin International Ltd holding a stake of 69.98 per cent and Zhong Zhuo Ye International Ltd 30pc.

Both the companies are wholly owned by State Grid International Engineering Ltd, a 100pc subsidiary of China Electric Power Equipment and Technical Company (CET) which in turn is 100pc owned by State Grid Cooperation of China (SGCC).

The SPV will be required to achieve commercial operation date (COD) of the transmission line by March 1, 2021 and will be empowered under the licence to run it for 25 years. The project is expected to be completed at a cost of $2.1 billion. The government is extending a series of tax concessions to the project.

Nepra said it issued the licence after consultations with all the relevant stakeholders to ensure that more than 4,000 megawatts of electricity to be produced in south of the country could be transported to the north, mostly the Punjab-based load centres and was satisfied with the credentials of the contractors.

The CET has carried out major transmission line projects in Ethiopia, China, Pakistan and Myanmar etc and had very rich experience as engineering, procurement and construction (EPC) contractor in construction of similar projects.

Regarding the financial health of the company, Nepra said the SPV had been incorporated in September 2015 and did not have any substantial assets as there was no significant activity of the project. It said the CET which will be working as EPC contractor had a total assets of $1.97bn. Also based on financial health of the sponsors, various Chinese banks (HSBC, UOB and CMBCL) had expressed their interest to finance the debt of the project.

Moreover, the regulator said the project was a priority project of China-Pakistan Economic Corridor (CPEC) and hence the project sponsors including SGCC and CET had strong financial health and possess the required resources to carry out the project.

The proposed 660kV High Voltage Direct Current (HVDC) transmission facilities will be connecting Matiari converter station (about 38km northeast to Hyderabad) and Lahore converter station (about 40km southwest of Lahore).

The proposed project will be passing through Sindh and Punjab and the necessary Environmental Social Impact Assessment (ESIA) had been carried out and cleared by the respective environmental protection agencies.

The project will be built on build, own, operate and transfer (BOOT) basis and will be handed over to NTDC after 25 years.

The construction of the project will be the responsibility of PMLTCPL including the operation and maintenance (O&M) of the converter stations at Matiari and Lahore, while NTDC will be responsible for the O&M of the transmission line part of the project for which it will incorporate a separate legal entity.

The regulator said both the PMLTCPL and NTDC had confirmed that maximum efforts were being made to select the shortest possible route duly considering the future transmission plans, social and environment aspect and to reduce the construction cost, land cost and associated maintenance and security costs.

Regarding the timely completion of 4,000MW of electric power projects so that the full capacity of the HVDC could be utilised, both NTDC and PMLTCPL committed to have proper coordination with various developers of the generation projects to ensure its optimal capacity utilisation.

The licence requires that the option of transfer of technology and future HVDC projects had been duly agreed and covered in the already initialled service and implementation agreements.

Regarding the provision of bi-directional transmission arrangement based on future requirements, the SPV gave an undertaking that 80pc of the contracted capacity will be available for reverse transmission after COD.

The licence required that shareholdings of CET in the project company will not be diluted during lock-in period ie up to six years from the COD of the project. Nepra had already allowed last year a 74-paisa per unit levilised tariff for the project.
 
After watching this i believe that we are no more in mess
 
G-B: Hydel project’s feasibility conducted

SKARDU: The Water and Power Development Authority (Wapda) has completed the feasibility report of the 34.5-megawatt Harpo-Skardu Hydropower Project. Iltaf Qadir, the project director, updated reporters on the progress achieved. The project will be completed at an estimated cost of over Rs 9.5 billion in three years, he said, adding that the German Department KFOW and AFD of France will donate 80% while 20% would be sourced from the Public Sector Development Programme. “The project will help in overcoming energy shortage in Baltistan division,” he said. Qadir said the mega project will also help in promoting infant industrial units.
 

Latest posts

Pakistan Affairs Latest Posts

Back
Top Bottom