What's new

Diamer Basha Dam construction Updates

.
DG FWO visited and inspected the progress and pace of the work of Diamer Basha Dam on 30 December 2020. Base camp and site offices have been established at the site recently. Work on connecting roads to dam site and construction of temporary / permanent bridges is ongoing.

Courtesy: FWO



1609513217366.png





1609513245992.png
 
. .
I hope they build a sediment bypass tunnel further up the valley. It will allow the rich sediment to continue down the river and extend the life of the dam as well as the efficiency of the power generation turbines.
 
.
I was in Chilas last year

and didnt even realise this was under construction

wish I visited now
 
.
What’s the current expect date this dam will be finished being physically built? And what is the expected final cost?
 
. .
DG FWO, along with his team, visited and inspected the progress of work at Diamer Basha Dam today. During the visit, he was briefed by Project Director and Chief Engineer regarding on-going construction works. DG showed his satisfaction and appreciated the quality and pace of works being done by FWO team.



1613226595824.png





1613226623657.png




1613227088618.png
 
. .
KKH upgradation/relocation for Bhasha dam. 100Km existing road will be submerged in reservoir and 140 Km long relocated KKH is under construction at higher elevation.

Credits: HAKAS



1615577392203.png






1615577486478.png





1615577511564.png
 
. .
Construction work on Bhasha, Tangir projects reviewed


The Newspaper'
March 26, 2021

The construction work on 21MW Tangir Hydropower Project, meant for providing electricity to the people in various areas during construction phase of Diamer Bhasha Dam, has commenced. — AFP/File



The construction work on 21MW Tangir Hydropower Project, meant for providing electricity to the people in various areas during construction phase of Diamer Bhasha Dam, has commenced. — AFP/File


LAHORE: The construction work on 21MW Tangir Hydropower Project, meant for providing electricity to the people in various areas during construction phase of Diamer Bhasha Dam, has commenced, according to the Water and Power Development Authority (Wapda).

The construction works on eight sites of Diamer Bhasha Dam and nine of the Dasu Hydropower projects are also underway these days on a fast-track basis.

Bhasha Dam project sites where the construction work was going on include access tunnel, access roads, upstream and downstream cable bridges, a senior official told Wapda Chairman retired Lt Gen Muzammil Hussain who visited the area on Wednesday.

During the visit, the Wapda chairman reviewed construction work on Bhasha as well as Tangir hydropower projects.

Speaking on the occasion, the Wapda chief said that construction work on Bhasha Dam was progressing despite the Covid-19 pandemic. He, however, maintained that the project authorities must ensure achieving major construction milestones in accordance with the timelines set for this purpose.

Gen Hussain opened the newly-constructed cable way bridge across River Indus. Rest of three such bridges are scheduled to be completed in April and May one after the other for swift mobilisation on both banks of the river during high-flow season.

Pontoon bridge across the River Indus had already been completed ahead of schedule in December last year to facilitate mobilisation of machinery and workforce during the current low-flow season.

Diamer Bhasha Dam will have a gross water storage capacity of 8.1 MAF to irrigate 1.23 million acres of additional land. With installed power generation capacity of 4,500 MW, the project will provide more than 18 billion units per annum to the National Grid.

Earlier, the Wapda chairman witnessed construction activities on Dasu Hydropower Project Stage-I, being built across River Indus upstream Dasu town in Kohistan District of Khyber Pakhtunkhwa. During the briefing about progress on the project, he was informed that the construction work on nine different sites is in progress.

He was told that river diversion works are expected to be completed by the end of this year. Afterwards, the mighty Indus would pass through the two diversion tunnels paving the way for construction of the main dam.

The Dasu Hydropower Project will be completed in two stages. Wapda is currently working on 2,160 MW-Stage-I, likely to be completed in 2025.The Stage-I will provide 12bn green and low-cost electricity to the national grid annually while the Stage-II will also contribute another 9bn units per annum.


Published in Dawn, March 26th, 2021
 
.
WAPDA Chairman reviews construction on Diamer Bash Dam, Dasu Project

‘Construction work on Diamer Basha Dam, Dasu Project progressing at good pace’

1616797637353.png




March 25, 2021: Pakistan Water and Power Development Authority (WAPDA) Chairman Lt Gen Muzammil Hussain (Retd) today visited Diamer Basha Dam and Dasu Hydropower Project to review construction work on the two mega projects.

During his visit to Diamer Basha Dam being constructed on River Indus downstream of Chilas town in Gilgit Baltistan, the Chairman was briefed that construction work on as many as 8 different sites in project area is underway. The construction sites included access tunnel, access roads, upstream and downstream cable bridges. The construction work on 21 MW Tangir Hydropower Project, meant for providing electricity during construction phase of Diamer Basha Dam, has also commenced, it was further briefed.

Speaking on the occasion, WAPDA Chairman said that construction work on Diamer Basha Dam is progressing ahead despite Covid-19 Pandemic that has, adversely affected the whole world. He, however, maintained that the project authorities must ensure achieving major construction milestones in accordance with the timelines set for the purpose.

The Chairman also opened the newly constructed cable way bridge across River Indus. Rest of three such bridges are scheduled to be completed in April and May one after the other for swift mobilization on both banks of the River during high flow season. Pontoon bridge across the River Indus had already been completed ahead of schedule in December last year to facilitate mobilization of machinery and workforce during the current low flow season.

Diamer Basha Dam will have a gross water storage capacity of 8.1 MAF to irrigate 1.23 million acres of additional land. With installed power generation capacity of 4500 MW, the project will provide more than 18 billion units per annum to the National Grid.

Earlier, WAPDA Chairman also witnessed construction activities on Dasu Hydropower Project Stage-I,
being built across River Indus upstream Dasu town in Kohistan District of Khyber Pakhtunkhwa.

During a briefing about progress on the project, the Chairman was apprised that construction work on 9 different sites is in progress. It was briefed that river diversion works are expected to be completed by end of this year. Afterwards, the mighty Indus would pass through the two diversion tunnels paving the way to constructing the Main Dam. The Chairman reviewed construction work on diversion tunnels and power house during the visit.

The 4320 MW-Dasu Hydropower Project will be completed in two stages. At present, WAPDA is working on 2160 MW-Stage-I, likely to be completed in 2025. The Stage-I will provide 12 billion green and low-cost electricity to the National Grid annually while the Stage-II will also contribute another 9 billion units to the system per annum.
 
. . .

Pakistan Affairs Latest Posts

Back
Top Bottom