From the Wapda 2013 report, Basha dam is underconstrution and will be completed by 2020-21.
While Dasu 4300mw will start this year (if everything goes right) and finish by 2026, i think this include Phase-I and Phase-II. Whlile Bunji 7100mw will start in 2017 and finish by 2024-25.
Basha dam:
Strategy
After approval of FODP/ADB Report on Water Sector Task Force by Federal Cabinet new strategy to be
adopted.
In case of non commitment of World Bank/ADB for financing Diamer Basha Dam Project an alternate financing
plan needs to be prepared.
GoP to provide funds for land acquisition.
80% of the cost of project will be met through loan/supplier credit/buyer’s credit.
20% of the cost of the project will be met through Govt. funding, domestic loan/local bonds (Sukuk) and PSDP.
Foreign financing will be made through Donor Agency/ADB//IDB/Middle East Donors/Buyer
Credits/Supplier’s Credit
Special request will be made to Islamic Development Bank, Asian Development Bank, Kuwait Development
Fund, Saudi Development Fund, Qatar Development Fund, Abu Dhabi Fund for investing in Diamer Basha Dam
Project.
Special request may be made to USAID to support this project as signatory project in Pakistan.
Consortium will be made comprising of Chinese Turkish and other Civil Contractors.
Consortium will also be made for supplying Electro-Mechanical equipment as Supplier’s Credit.
PRESENT STATUS
Detailed Engineering Design of Diamer Basha Dam Project (DBDP) was completed in June-2008.
PC-I for Land Acquisition and Resettlement was approved by Executive Committee of National Economic
Council (ECNEC) on 6.11.2008 for Rs. 60 billion.
Main PC-I for DBDP was approved by ECNEC on 20.08.2009 for Rs.894.257 billion.
Resolution on Consensus of Diamer Basha Dam Project approved from Council of Common Interest (CCI) on
18.07.2010 headed by Prime Minister of Pakistan.
Bridge at Thakot on Indus River is completed by NHA for transportation of material and heavy machinery for
construction of Diamer Basha Dam Project.
Priority Land Acquisition has started.
Rs.6.563 billion have been released to the Government of Gilgit-Baltistan for acquisition of land and 1783 Acres
of land has been acquired.
25
Rs.262 million was released in to D.C. Kohistan for acquisition of land and 162 Acres land has been acquired of
Khyber Pakhtunkhwa area.
A vocational Training Institute has been setup.
Inauguration ceremony for commencement of works of Diamer asha Dam Project has been carried out by the
Prime Minister of Pakistan on 18.10.2011.
http://www.wapda.gov.pk/pdf/potentialPakistan . pdf