What's new

China Pakistan Economic Corridor (CPEC) | Power Plants

,.,.,.,.,...
Diamer Basha Dam :

Construction Work is in Progress
Gross capacity: 8.1 MAF
Installed capacity: 4,500 MW


1658010386452.png





1658010410928.png





1658010451552.png





1658010484717.png
 
.
.,.,.,.,.
Suki Kinari Hydropower Project located on Kunhar River in beautiful valley of Kaghan, Khyber Pakhtunkhwa.
It will generate over 884 MW electricity, and is expected to be completed by end of 2023.

1658061195705.png




1658061225231.png




1658061256098.png




1658061298624.png
 
.
,.,.,.,.
Successful Test Run of 1,263MW Thermal Power Plant Completed in Jhang

The China Machinery Engineering Corporation (CMEC) has successfully completed a seven-day reliability test run of the 1,263 MW Thermal Power Plant Unit-1 in district Jhang, Punjab.

A spokesperson for the corporation said that Gas Turbine 1’s (GT-1) commercial operations will begin on 6 July after the stopped machines are tested for their heating and cooling.

The plant completed its initial test by generating 403 MW instead of its guaranteed 400 MW.
 
. .
.,.,
Suki Kinari Hydropower Project located on Kunhar River in the beautiful valley of Kaghan, Khyber Pakhtunkhwa,
It will generate over 884 MW of electricity and is expected to be completed by end of 2023.


1658528940546.png




1658528991937.png




1658529035449.png





1658529062790.png
 
.
.,.,
Suki Kinari Hydropower Project, a clean energy project under CPEC umbrella.
It will add 884MW to the national grid after completion and entering into commercial operation.


1658667363676.png





1658667396194.png




1658667437473.png
 
. .

Solar plant to replace 300MW Gwadar coal power project​


By Staff Reporter | thenews Jul 26, 2022



ISLAMABAD: The Power Division has decided to abandon the 300MW imported coal-based power plant at Gwadar and replace it with a solar plant.
The project was conceived under the CPEC and approved in 2016, but its formal construction had not started. Now the government wants China to install a solar power plant of the same capacity after the government decided not to install any new power plant based on imported fuel in the future.
“We have decided to abandon the project, but we will have to take up the issue at various CPEC forums with our Chinese counterparts. CPEC projects have sensitivity and importance which is why the Power Division’s decision to replace the imported coal-based project at Gwadar with a solar plant is being kept at a low profile,” an official said.
Federal Minister for Power Division Khurram Dastgir Khan also hinted the government wanted the Chinese power plant at Gwadar to be replaced with a solar power plant of 300MW. Talking to The News, he also added that the government had decided to ban new power plants based on imported fuel and would add new capacity to electricity generation based on local fuel, such as Thar coal, wind, solar, and hydel. “However, the government will continue the policy to install more nuclear power plants,” he added.
More importantly, the minister said, the government has also decided to convert the existing imported coal-based power plants of 3,960MW, including the Port Qasim plant, Sahiwal power plant and China Hub plant, each having the capacity to generate 1,320MW of electricity, to local coal. The fuel import bill had eaten up almost $20 billion in the first 11 months of the last fiscal 2021-22. The initiative is being taken to scale down the fuel import bill and reduce reliance on imported fuel for power generation. The minister said the process to convert the three projects to local coal would take investment and time as boilers of the plants would need some specific changes for calibration with Thar coal.
The Joint Cooperation Committee (JCC) for the CPEC had decided in its 6th meeting held in Beijing in December 2016 that a 300MW imported coal-fired power project must be developed on a fast-track basis at Gwadar. The tariff of the project was determined in September 2019, land for the project was acquired in February 2020 and the project management was signed on April 8, 2021. The Nepra also issued a generation licence to the project management. However, the financial close of the project has not yet been completed as it is still under process. The project is still on the list of under-construction CPEC projects. However, its construction has not started yet. That is why top officials of the Power Division have decided to abandon the project and replace it with a solar power plant under its new policy not to install a new power plant base on imported coal in future.
Pakistan is currently importing 30 to 70MW of electricity from Iran under an agreement of 110MW. Sometimes, Pakistan has some fluctuation in electricity import because of demand in Iran. Pakistan had inked a new agreement of importing 100MW electricity for which a transmission line would be laid from Polan (Iran) to Gwadar by the end of 2022, or the start of 2023. The government has also increased its emphasis on laying its own infrastructure in Balochistan and the NTDC will lay a high transmission line of 500kv from Makran coast to Gwadar.
 
.

Solar plant to replace 300MW Gwadar coal power project​


By Staff Reporter | thenews Jul 26, 2022



ISLAMABAD: The Power Division has decided to abandon the 300MW imported coal-based power plant at Gwadar and replace it with a solar plant.
The project was conceived under the CPEC and approved in 2016, but its formal construction had not started. Now the government wants China to install a solar power plant of the same capacity after the government decided not to install any new power plant based on imported fuel in the future.
“We have decided to abandon the project, but we will have to take up the issue at various CPEC forums with our Chinese counterparts. CPEC projects have sensitivity and importance which is why the Power Division’s decision to replace the imported coal-based project at Gwadar with a solar plant is being kept at a low profile,” an official said.
Federal Minister for Power Division Khurram Dastgir Khan also hinted the government wanted the Chinese power plant at Gwadar to be replaced with a solar power plant of 300MW. Talking to The News, he also added that the government had decided to ban new power plants based on imported fuel and would add new capacity to electricity generation based on local fuel, such as Thar coal, wind, solar, and hydel. “However, the government will continue the policy to install more nuclear power plants,” he added.
More importantly, the minister said, the government has also decided to convert the existing imported coal-based power plants of 3,960MW, including the Port Qasim plant, Sahiwal power plant and China Hub plant, each having the capacity to generate 1,320MW of electricity, to local coal. The fuel import bill had eaten up almost $20 billion in the first 11 months of the last fiscal 2021-22. The initiative is being taken to scale down the fuel import bill and reduce reliance on imported fuel for power generation. The minister said the process to convert the three projects to local coal would take investment and time as boilers of the plants would need some specific changes for calibration with Thar coal.
The Joint Cooperation Committee (JCC) for the CPEC had decided in its 6th meeting held in Beijing in December 2016 that a 300MW imported coal-fired power project must be developed on a fast-track basis at Gwadar. The tariff of the project was determined in September 2019, land for the project was acquired in February 2020 and the project management was signed on April 8, 2021. The Nepra also issued a generation licence to the project management. However, the financial close of the project has not yet been completed as it is still under process. The project is still on the list of under-construction CPEC projects. However, its construction has not started yet. That is why top officials of the Power Division have decided to abandon the project and replace it with a solar power plant under its new policy not to install a new power plant base on imported coal in future.
Pakistan is currently importing 30 to 70MW of electricity from Iran under an agreement of 110MW. Sometimes, Pakistan has some fluctuation in electricity import because of demand in Iran. Pakistan had inked a new agreement of importing 100MW electricity for which a transmission line would be laid from Polan (Iran) to Gwadar by the end of 2022, or the start of 2023. The government has also increased its emphasis on laying its own infrastructure in Balochistan and the NTDC will lay a high transmission line of 500kv from Makran coast to Gwadar.
What would happen if the US attacks Iran and knocks out the Iranian grid, hypothetically speaking of course?-"Pakistan is currently importing 30 to 70MW of electricity from Iran under an agreement of 110MW."
 
.
The areas of Pakistan that depend on Iranian electricity would lose power. 30 to 70 MW isn't a whole lot though, probably just covers the border areas.
 
.

Solar plant to replace 300MW Gwadar coal power project​


By Staff Reporter | thenews Jul 26, 2022



ISLAMABAD: The Power Division has decided to abandon the 300MW imported coal-based power plant at Gwadar and replace it with a solar plant.
The project was conceived under the CPEC and approved in 2016, but its formal construction had not started. Now the government wants China to install a solar power plant of the same capacity after the government decided not to install any new power plant based on imported fuel in the future.
“We have decided to abandon the project, but we will have to take up the issue at various CPEC forums with our Chinese counterparts. CPEC projects have sensitivity and importance which is why the Power Division’s decision to replace the imported coal-based project at Gwadar with a solar plant is being kept at a low profile,” an official said.
Federal Minister for Power Division Khurram Dastgir Khan also hinted the government wanted the Chinese power plant at Gwadar to be replaced with a solar power plant of 300MW. Talking to The News, he also added that the government had decided to ban new power plants based on imported fuel and would add new capacity to electricity generation based on local fuel, such as Thar coal, wind, solar, and hydel. “However, the government will continue the policy to install more nuclear power plants,” he added.
More importantly, the minister said, the government has also decided to convert the existing imported coal-based power plants of 3,960MW, including the Port Qasim plant, Sahiwal power plant and China Hub plant, each having the capacity to generate 1,320MW of electricity, to local coal. The fuel import bill had eaten up almost $20 billion in the first 11 months of the last fiscal 2021-22. The initiative is being taken to scale down the fuel import bill and reduce reliance on imported fuel for power generation. The minister said the process to convert the three projects to local coal would take investment and time as boilers of the plants would need some specific changes for calibration with Thar coal.
The Joint Cooperation Committee (JCC) for the CPEC had decided in its 6th meeting held in Beijing in December 2016 that a 300MW imported coal-fired power project must be developed on a fast-track basis at Gwadar. The tariff of the project was determined in September 2019, land for the project was acquired in February 2020 and the project management was signed on April 8, 2021. The Nepra also issued a generation licence to the project management. However, the financial close of the project has not yet been completed as it is still under process. The project is still on the list of under-construction CPEC projects. However, its construction has not started yet. That is why top officials of the Power Division have decided to abandon the project and replace it with a solar power plant under its new policy not to install a new power plant base on imported coal in future.
Pakistan is currently importing 30 to 70MW of electricity from Iran under an agreement of 110MW. Sometimes, Pakistan has some fluctuation in electricity import because of demand in Iran. Pakistan had inked a new agreement of importing 100MW electricity for which a transmission line would be laid from Polan (Iran) to Gwadar by the end of 2022, or the start of 2023. The government has also increased its emphasis on laying its own infrastructure in Balochistan and the NTDC will lay a high transmission line of 500kv from Makran coast to Gwadar.
On the news of building a “high transmission line” across the Makran coast, should Pakistan considering building some of SEZs on the coast rather than so far inland. It would help keep production costs down but would require workers to move to these areas. It’s the same model for a lot of industrializing nations.
 
.
On the news of building a “high transmission line” across the Makran coast, should Pakistan considering building some of SEZs on the coast rather than so far inland. It would help keep production costs down but would require workers to move to these areas. It’s the same model for a lot of industrializing nations.
I'd focus on getting Gwadar fully operational first, current energy supply isn't enough as companies so far have had to rely on generators importing fuel. Once you get Gwadar running smoothly you can build future SEZs quickly based on lessons learned.
 
.
I'd focus on getting Gwadar fully operational first, current energy supply isn't enough as companies so far have had to rely on generators importing fuel. Once you get Gwadar running smoothly you can build future SEZs quickly based on lessons learned.
Fair enough
 
.
.,.,
Jul 27, 2022
NAVEED BUTT

ISLAMABAD: Power projects including 1124 MW Kohala and 700.7 MW Azad Pattan HPPs as well as 1,320 MW Thar Coal power plant project will be taken up in the coming meeting of the Pakistan-China Joint Energy Working Group (JEWG) which would be held in the first week of the next month (August).

The Power Division highlighted the agenda for the forthcoming 9th JEWG meeting and discussed power projects in pre Joint Coordination Committee meeting held on Tuesday, here in Islamabad.

Federal Minister for Planning Development and Special Initiatives Ahsan Iqbal presided over the meeting to review the progress made in preparation for the 11th JCC meeting expected to be convened next month.
 
. .
Back
Top Bottom