On 6th September 2021, the last concrete has been poured for Azad Pattan Bridge located within the reservoir area of Karot Hydropower Project. The total length of the bridge is 200m & the bridge deck width is 11.5m.
The already existing bridge will be inundated in the Karot HPP Reservoir. This is another step closer, and at the same time, it laid a solid foundation for the reservoir filling goal.
Mohmand Dam Hydropower Project - 800 MW Under Construction since September 2019
Gross Storage 1.2 MAF
Annual Energy Production 2,862 GWh
Completion date: 2025
- Location: on Kunhar River, Kaghan Valley, Manshera, KPK
- Project Cost: 1.9 billion USD
- Under strategic CPEC framework.
- Construction Started: early of 2017
- Completion Date: December, 2022
The stator of Unit 4 of the Suki Kinari Hydropower Station in Kaghan Valley Pakistan has successfully been hoisted into the pit on September 8. This is the first unit that has completed this step..
The pressure tunnel of Lawi Hydropower Project, 69 MW , Chitral, successfully breakthrough.
The total length is 741m with one access adit of 146 meter length.
The diameter of the tunnel is 3.4m with circular shape.
Under Construction Karot Hydropower Project - 720MW
Located on Jhelum river and first Hydel Project of CPEC. \
The Project physicals progress is around 93% and first unit commissioning is expected in early 2022.