What's new

China Pakistan Economic Corridor (CPEC) | Power Plants

Construction work at Dasu Dam in progress.


1619101789298.png






1619101812648.png





1619101857764.png
 
.
Signing of Agreement 1124 MW Kohala Hydropower Project under CPEC.


1619180465407.png
 
.
Cold functional tests were completed on 20th April at unit 3 of the Karachi nuclear power plant in Pakistan, China National Nuclear Corporation (CNNC) has announced.

Units 2 and 3 at the site are China's first exports of the Hualong One reactor design, promoted on the international market as the HPR1000. Karachi 2 was synchronised with the electricity grid last month.

Completion of the cold testing of Karachi 3 was overseen by the Pakistan Nuclear Regulatory Authority and the Pakistan Atomic Energy Commission (PAEC), CNNC said.

The successful completion of the cold testing means that the main work of the nuclear island.

installation project of the unit has been completed and the unit has entered the system commissioning stage, CNNC said. Cold testing will be followed by thermal testing, then first fuel loading and finally grid-connected power generation.
 
.
CPEC: Kohala Hydropower Project.

Capacity: 1124 Megawatts.
Investment: $2.4 Billion
Location: Jhelum River - AJK.
Completion Date: 2027


1619270839424.png
 
.
ISLAMABAD: The government of Azad Jammu and Kashmir (AJK) and Chinese Three Gorges Company on Friday signed agreements related to 1,124 megawatt Kohala Hydel Power Project- Implementation and Water Usage under China Pakistan Economic Corridor (CPEC).

The project would attract a foreign investment of $2.4 billion under the umbrella of CPEC.

This was announced by CPEC Authority, Chairman, Lieutenant General Asim Saleem Bajwa (retd), on his Twitter handle.

“The signing ceremony for 1,124 MW Kohala Hydel Power Project- Implementation and Water Usage Agreements held between AJK Government and China Three Gorges Company,” the Chairman CPEC Authority tweeted.

Federal Minister of Energy Hammad Azhar, AJK Prime Minister Raja Farooq Haider and others officials were present on the occasion.

The Kohala Hydropower Project is a proposed run-of-the-river high head project, located near Kohala, in Azad Kashmir.

The agreement for the project was finalised in 2020 and later it was formally signed in a ceremony attended by the Pakistani Prime Minister, and Chinese ambassador.

China Three Gorges Corporation (CTGC), the state-owned hydropower developer, had won the right to develop a hydroelectric dam in Pakistan on January 7, 2015. It will be Chinese company’s largest investment in Pakistan.
 
.
Mohmand Dam Hydropower Project - 800 MW
Under Construction since September 2019
Gross Storage 1.2 MAF
Annual Energy Production 2,862 GWh
Completion date: 2025


1619356909412.png




1619356960890.png
 
. .
Under Construction Dasu Hydropower Project - 4320MW (First Stage: 2,160MW)

Concrete works at the inlet of Diversion Tunnel B is in progress.

Credits: Engr. Asim


1619359326001.png





1619359354575.png
 
. .
Dam site of Suki Kinari Hydropower Project -884MW
Preparations are going on for final diversion of River Kunhar through Lower Spillway Bays.



1619464524462.png
 
.
Another important Landmark has been achieved at Suki Kinari Hdyropower Project (884MW)
Today 30th April, 2021 at about 110hrs, River Kunhar has been diverted through Spillway bays to start the filling of Asphalt core, Rockfill dam. To Celebrate this, a ceremony has been held at construction site and the representative of all stakeholders participated.

Congratulation to all and salute to those who have worked day and night to make this happen.


1619803280126.png




1619803308950.png




1619803335896.png
 
. . .
Clicks taking during pavement marking at RAR-01 Trial Section..
Dasu Hydropower Project


1619988187016.png




1619990494380.png
 
.
The Karot Hydropower Project is a 720 MW run-of-river project to be built on the Jhelum River, Rawalpindi district.
720 MW Karot_Hydro Power_Project Powerhouse and Intake
#China #Pakistan Economic Corridor

95791247_2717882088339472_6642038512331784192_o.jpg





96545166_2717882158339465_1255489000127332352_o.jpg
Can't see the images.
We need to see renewable power projects like Terawatt Solar farms, Terawatt wind farms and small water powered generators put in fast flowing streams and rivers. But coal power stations are better than the daily load shedding Pakistanis were suffering.
 
Last edited:
.

Latest posts

Pakistan Defence Latest Posts

Back