China Pakistan Economic Corridor (CPEC) | Power Plants

.
Suki Kinari Hydro Power Project



1602768028100.png





1602768141030.png
 
. .
3rd Men's Basketball Tournament - Karot Hydropower Project ( 720MW ) Apart from the professional duties, the recreational activities at Construction site plays an important role to refresh the workers living far from their families especially in this COVID19 situation.


1602959204384.png

.


1602959514587.png
 
.
A CPEC Project in Kaghan Valley - Suki Kinari Hydropower Project ( 884MW )

The Underground Structures especially Powerhouse and Transformer Hall activities are going on with full momentum to catch up the planned completion date i.e Dec, 2022.



1603134382967.png




1603134437038.png
 
. . .
Kohala Hydel Project, AJK


Project


Kohala Hydel Project, AJK




Primary Energy Input


Hydel
Installed Capacity (MW)1100
LocationJhelum River near Muzaffarabad
Estimated Cost (US $ Million)2364.05
Executing Company / SponsorsCTG/CWEI (China Three Gorges) / (CWE Investment Crop)
FinancingIndependent Power Producer (IPP)
Coordinating MinistryMinistry of Energy (Power Division)
Supervising AgencyPrivate Power and Infrastructure Board (PPIB)

Kohala Hydel Project, AJK
  • Feasibility Study (stage-1) Tariff Announced by NEPRA
  • Land Acquisition process started
  • Environmental NOC issued by AJ&K EPA
  • LOS issued (Under Financial Closing)
  • Tripartite agreement signed on 25th June 2020
  • Expected Commercial Operation Date (COD) 2026













.
 
Last edited:
.
700MW Azad pattan hydropower_project nears financial close.

Pakistan and China have step another step towards achieving the financial close of the 700MW Azad Pattan Hydropower Project, which is part of the China-Pakistan Economic Corridor (CPEC), by signing more agreements in this regard on Tuesday.

“The project agreements namely ‘GoAJ&K Implementation Agreement’ and ‘GoAJ&K Water Use Agreement’ were signed by Azad Jammu Kashmir Power Secretary Zafar Mahmood Khan and Azad Pattan Power Private Limited CEO Li Xiaotao,” a statement issued by the Ministry of Energy on Tuesday read. “With an investment of over $1.35 billion, the Azad Pattan project won’t be relying on imported fuel, enabling the country to move towards cheaper and greener power generation.”

AJK Prime Minister Raja Farooq Haider Khan, Federal Power Minister Omer Ayub Khan, Planning Minister Asad Umar, CPEC Authority Chairman Lt Gen (r) Asim Saleem Bajwa, AJK Chief Secretary Dr Shahzad Khan Bangash and Private Power and Infrastructure Board (PPIB) Managing Director Shah Jahan Mirza were also present on the occasion.

As per the statement, today’s development will further pave the way for achievement of financial close of the project.

Earlier, a Letter of Support (LOS) was issued by PPIB to Azad Pattan HPP, which is a Run-off-the River Scheme on River Jhelum located at dual boundary between AJ&K (District Bagh) and Punjab (District Rawalpindi). China Gezhouba Group and Laraib Group Pakistan are the shareholders of the project.

The consortium of lenders consists of China Development Bank, China Construction Bank, Industrial & Commercial Bank of China and Bank of China. Azad Pattan Project is being implemented by PPIB.

Moreover, after completion of construction work, tourism activities around reservoir/lake and water sports, fishing etc. are also associated avenues for earning valuable revenue.




1606924273977.png


...
 
.
1607007183808.png




Under Construction Dasu Hydropower Project



The project is expected to start electricity generation in the second half of 2024, while all six units of the Stage-I, with cumulative generation capacity of 2160MW, will be completed by early 2025.

Dasu Hydropower Project is being constructed on the River Indus upstream of Dasu town. WAPDA is implementing the project in two stages – each stage having a generation capacity of 2160MW. On completion,

Stage-I of the project will contribute more than 12 billion units of electricity per annum to the National Grid.
The Stage-II, after its completion, will also provide another 9 billion units to the system every year.



1607007209558.png
 
. . . .
Next-generation KANUPP-2, 1100 MW nuclear power plant to be fully operational by April 2021 and KANUPP-3 ,1100 MW nuclear power plant by October 2021.

According to PAEC, the KANUPP-2 reactor was loaded with fuel on 1st December 2020 after approval from the #Pakistan Nuclear Regulatory Authority (PNRA). Director General Strategic Plans Division (SPD) Lieutenant General Nadeem Zaki Manj, Chairman PAEC Muhammad Naeem, member power committee of the PAEC, and top officials of China graced the occasion with their presence.

The PAEC spokesperson said, “Its construction began in August 2015 and after an operational examination, it will begin producing power from April 2021.” The KANUPP-2 and KANUPP-3 reactor are both third-generation atomic power plants based on the Hualong One reactor units that are supplied by the Chinese. Both of these reactors will have the capability to produce 1100 MW of electricity with KANUPP-3 joining the grid in October 2021. In comparison, the KANUPP-1 power plant had a maximum capacity of just 137 MW.



1607366936406.png
 
.
Under Construction
4320 MW Dasu Hydropower Project.

Dasu Dam Stage 1 Completion: 2025
Power Generation of stage 1: 2160 MW

Dasu Dam , Kohistan. KP




1607432819887.png





1607432978266.png





1607433004365.png
 
.