Dhaka Metrorail MRT Line-6 latest status, 3 KM rails laid, terminals almost completed
Progress Report for MRT-6 as of January 2020
https://dmtcl.portal.gov.bd/sites/de...bae6ba65a7.pdf
CP02 (associated works of the Depot)- 62%
CP03 & CP04 (Uttara North to Agargaon)- 66%
CP05 (Agargaon to Karwan Bazaar)- 38.20%
CP06 (Karwan Bazaar to Motijheel)- 40.25%
CP07 (Mechanical and Electrical works)- 32.30%
CP08 (Rolling stocks and Depot equipment)- 20.50%
Progress for other MRT lines (some underground)
MRT Line-1
Detailed study, survey and basic design have been completed. Work on detailed design and land acquisition for the depot is in progress. Works for MRT Line-1 will hopefully start in December 2020.
MRT Line-5 Northern Route
Feasibility Study has been completed. The Consultant company for Engineering services is being chosen now. Detailed study, survey and basic design will start in March 2020.
MRT Line-5 Southern Route
Project Readiness Financing (PRF) has been signed with the relevant authorities. Request For Proposal (RFP) has been issued to appoint a Consultant company. Feasibility study will hopefully start in July 2020.
MRT Line-2
The basic study has already begun. Hopefully, the Preliminary study will start in April 2020.
----------------------------------------------------------------------------------------------------
Latest updates on Matarbari (near Cox's Bazaar) Japanese-led Super-efficient Power Project and Deep Sea Port. Sorry Bengali only.