ISLAMABAD: WAPDA has decided to provide Rs98 billion from its resources to build the Diamer Bhasha and Mohmand Dam.
According to News, WAPDA has prepared a plan to provide funds for the construction of Diamer Bhasha and Mohmand Dams, Bhasha Dam will cost about Rs1,500 billion, while the estimation of the cost of Mohmand Dam is 309 billion, for Dams WAPDA has decided to give Rs98 billion from its own resources.
According to WAPDA sources, the construction work on the Mohmand Dam is expected in early 2019, where the construction of Diamer Bhasha Dam will be started in the mid-2019, the Diamer Bhasha Dam will be complete in almost 9 years and the Mohmand Dam will be complete in almost 6 years.
WAPDA sources say that a special financial plan has been set up for the Diamer Bhasha Dam, the project will be constructed in two parts, the cost of the dam is required for the construction is around 300 billion rupees. For Dam Rs474 billion needed while approximately 751 billion rupees is required for the Power House needs.
According to the sources, funds for the Mohmand Dam will be administered in the form of a loan from Federal Government Annual Development Program, WAPDA Equity, Local and Foreign Banks and Financial Institutions, and this loan will be availed by WAPDA for its assets.
Sources said that there is no problem for the Diamer Bhasha and Mohmand Dams funds, the value of WAPDA’s assets is worth than 40 billion dollars, while the WAPDA sold 32 billion units of power central power agency last year Its value is more than Rs 65 billion
ISLAMABAD: WAPDA has decided to provide Rs98 billion from its resources to build the Diamer Bhasha and Mohmand Dam.
According to News, WAPDA has prepared a plan to provide funds for the construction of Diamer Bhasha and Mohmand Dams, Bhasha Dam will cost about Rs1,500 billion, while the estimation of the cost of Mohmand Dam is 309 billion, for Dams WAPDA has decided to give Rs98 billion from its own resources.
According to WAPDA sources, the construction work on the Mohmand Dam is expected in early 2019, where the construction of Diamer Bhasha Dam will be started in the mid-2019, the Diamer Bhasha Dam will be complete in almost 9 years and the Mohmand Dam will be complete in almost 6 years.
WAPDA sources say that a special financial plan has been set up for the Diamer Bhasha Dam, the project will be constructed in two parts, the cost of the dam is required for the construction is around 300 billion rupees. For Dam Rs474 billion needed while approximately 751 billion rupees is required for the Power House needs.
According to the sources, funds for the Mohmand Dam will be administered in the form of a loan from Federal Government Annual Development Program, WAPDA Equity, Local and Foreign Banks and Financial Institutions, and this loan will be availed by WAPDA for its assets.
Sources said that there is no problem for the Diamer Bhasha and Mohmand Dams funds, the value of WAPDA’s assets is worth than 40 billion dollars, while the WAPDA sold 32 billion units of power central power agency last year Its value is more than Rs 65 billion