Btw, you pointed out that Phase I should have been ready by 2014. But it's not possible to activate the full Phase I BMD system without multiple target testing. And this has been delayed due to the late allotment of land for the second test range. DRDO had planned to finish all the construction work by 2014-15 and finish development trials. But land approvals came only in 2017, hence why it has been delayed. The same with Phase II, it should have begun testing in 2016, but it's not possible without the second test range. BMD delays are not due to technical reasons. That's also why BMD sites have already been cleared for construction.
The same with the test facility in A&N Islands, which will be important for Phase II. Clearance came only last year.
So Phase I should finish the same year as the test range is ready. And Phase II could also start at the same time, perhaps even earlier. So best not to go by the dates that DRDO had announced. Things could move very quickly once the test range is ready.