DV RULES
SENIOR MEMBER
- Joined
- Jan 13, 2010
- Messages
- 4,078
- Reaction score
- -2
- Country
- Location
The Russian Navys fourth Project 11356 frigate will have its keel laid on Thursday, the Yantar shipyard said on Monday.
The start of construction work on the Admiral Butakov frigate was postponed in October 2012.
The Kaliningrad-based shipyard is to build a total of six Project 11356 frigates under a contract with the Defense Ministry.
The lead warship in the series, the Admiral Grigorovich, was laid down in December 2010, the second, the Admiral Essen, in July 2011 and the third, the Admiral Makarov, in February 2012.
The shipyard is to hand over the six warships to the Navy between 2014 and 2016.
Project 11356 frigates are designed for anti-ship and anti-submarine warfare on the high seas, and for anti-aircraft operations, both independently and as an escort ship. The vessels are armed with strike anti-ship and surface-to-air missiles, gun mounts, torpedoes and bombs, according to navaltoday.com.
Russia to Lay Keel for 4th Project 11356 Frigate | Defense | RIA Novosti
The start of construction work on the Admiral Butakov frigate was postponed in October 2012.
The Kaliningrad-based shipyard is to build a total of six Project 11356 frigates under a contract with the Defense Ministry.
The lead warship in the series, the Admiral Grigorovich, was laid down in December 2010, the second, the Admiral Essen, in July 2011 and the third, the Admiral Makarov, in February 2012.
The shipyard is to hand over the six warships to the Navy between 2014 and 2016.
Project 11356 frigates are designed for anti-ship and anti-submarine warfare on the high seas, and for anti-aircraft operations, both independently and as an escort ship. The vessels are armed with strike anti-ship and surface-to-air missiles, gun mounts, torpedoes and bombs, according to navaltoday.com.
Russia to Lay Keel for 4th Project 11356 Frigate | Defense | RIA Novosti