What's new

Pakistan gets $425 million loan to modernise transmission network

FalconsForPeace

SENIOR MEMBER
Joined
Sep 20, 2013
Messages
1,132
Reaction score
3
Country
Pakistan
Location
Pakistan
1734581-image-1528912693-371-640x480.jpg


Six months after its approval, Pakistan and the World Bank on Wednesday signed a $425-million loan agreement for bringing improvement in the country’s dilapidated electricity transmission network.



Economic Affairs Division Secretary Syed Ghazanfar Abbas Jilani and World Bank Country Director Patchamuthu Illangovan signed two agreements worth $565 million. These included a credit of $425 million to modernise the power transmission system and additional financing of $140 million for the Sindh Barrages Improvement Project.

The $425-million loan has been acquired on commercial terms that will be returned over a period of 21 years including a grace period of six years. The World Bank board had approved the loan in December last year, but the bureaucracy took six months to meet procedural requirements before signing the agreement.



The loan will be spent on modernising the national transmission network by rehabilitating selected 500-kilovolt and 220kv sub-stations and transmission lines.

The existing transmission system has the capacity to carry about 15,000-17,000 megawatts of electricity safely, which is substantially below the peak load of over 20,000MW, according to the World Bank. The objective of the project is to increase capacity and reliability of selected segments of the national transmission system and modernise key business processes of the National Transmission and Despatch Company (NTDC).

Aging and inadequate transmission and distribution systems exacerbated the problem. The World Bank said Pakistan’s recent efforts had been focused on increasing power generation capacity, but aging and increasingly unreliable transmission and distribution systems also imposed severe constraints.

There have been several instances of major system collapses, which appear to be increasing in frequency and severity.

In the distribution system, two key measures of system reliability, the System Average Interruption Duration Index (SAIDI) and the System Average Interruption Frequency Index (SAIFI), present a mixed picture, but suggest that in several distribution companies the quality of supply is deteriorating.

The regulator reports that most distribution systems do not meet the investment targets for repair and maintenance.

The project will support investments in high-priority transmission infrastructure, information and communication technology (ICT) and technical assistance for improved management and operations.

Total cost of the project is $536.33 million. The World Bank will provide $425 million whereas the remaining $111.33 million will be arranged by the NTDC.

The project targets include a three-fourth reduction in forced outages and 50% reduction in the frequency of forced outages. About 131-kilometre-long transmission lines are planned to be rehabilitated and 36 new sub-stations will be constructed.

Under the Sindh Barrages Improvement Project, the development objectives are to improve reliability and safety of the Guddu Barrage and strengthen the Sindh Irrigation Department’s capacity to operate and manage the barrage.

This additional financing will help to scale up activities under the original project, whose scope at present is limited to rehabilitating and modernising the Guddu Barrage.

Now, the project will also support rehabilitation and modernisation of the Sukkur Barrage as well as support improvement in the operation and maintenance of three Sindh barrages over the Indus River – Guddu, Sukkur and Kotri – through better coordination and monitoring.

Total estimated additional financing required is $152.2 million and the remaining $12 million will be provided by the government of Sindh.

https://tribune.com.pk/story/173458...-million-loan-modernise-transmission-network/
 
.
Hopefully it gets used where it is supposed to be and not in building someone's empire!
 
.
Good choice

Our electricity problem was never just about power generation it was a
lack of power production
poor transmission lines
theft of power
Corruption
Etc


We are now increasing power production
If we can improve the transmission lines and get a handle on power theft, corruption and bills not being paid then not only is loadshedding a thing of the past we will boost the economy
 
.
Good choice

Our electricity problem was never just about power generation it was a
lack of power production
poor transmission lines
theft of power
Corruption
Etc


We are now increasing power production
If we can improve the transmission lines and get a handle on power theft, corruption and bills not being paid then not only is loadshedding a thing of the past we will boost the economy
One thing i would suggest is to use digital electric meters o have seen them in chitral they automatically disable if the bill is not paid and can also be recharged online.
 
.
Finally there is investment in the Transmission and Distribution which will ease the LS issues for the Pakistani consumers. There has to be campaign to initiate modernizing the distribution in cities like Karachi and Lahore to reduce faults and breakdowns.
 
. .
Good choice

Our electricity problem was never just about power generation it was a
lack of power production
poor transmission lines
theft of power
Corruption
Etc


We are now increasing power production
If we can improve the transmission lines and get a handle on power theft, corruption and bills not being paid then not only is loadshedding a thing of the past we will boost the economy
The defaulters lie in highly influential industrialists and agricultural users at 400 billion rupees
Govt sector it self is 200 billion rupees

Govt sector is easy fix it just need improvement in book keeping or if provinces dont pay cut it from their NFA share

400 billion is difficult fix..govt doesny has the will to take that money and will blame small domestic users who breaky use 5% of total power
 
. .
Circular debt will not be eased thru modernization. It needs structural reform. And holding the debtees to account. But when the govt and its politicians themselves are the debted ones what to do?
 
. .

Pakistan Defence Latest Posts

Pakistan Affairs Latest Posts

Back
Top Bottom