Anthony Capaccio ACapaccio
August 24, 2016 — 7:07 AM EESTUpdated on August 25, 2016 — 1:46 AM EEST



  • Fighter is ‘on a path toward failing to deliver,’ Gilmore says
  • Memo came a week after Air Force declared its version ready

A week after the Air Force declared its version of Lockheed Martin Corp.’s F-35 jet ready for limited combat operations, the Pentagon’s top tester warned that the U.S. military’s costliest weapons program is still riddled with deficiencies.

“In fact the program is actually not on a path toward success but instead on a path toward failing to deliver” the aircraft’s full capabilities, “for which the Department is paying almost $400 billion by the scheduled end” of its development in 2018, Michael Gilmore, the Defense Department’s director of operational testing, said in an Aug. 9 memo obtained by Bloomberg News.

“Achieving full combat capability with the Joint Strike Fighter is at substantial risk” of not occurring before development is supposed to end and realistic combat testing begins, he said of the F-35.


The memo provides a timely reminder of an issue that the next president and defense secretary will inherit. They are scheduled to decide in 2019 whether to let the fighter jet move into full production, the most lucrative phase for Lockheed, the biggest U.S. defense contractor. It’s also an issue for U.S. allies that have committed to buy the plane, including the U.K., Italy, Australia, Japan and Israel.

The Air Force made its declaration of initial combat capability on Aug. 2, but “most of the limitations” previously identified with software, data fusion, electronic warfare and weapons employment continue, Gilmore wrote.

‘Far Behind’
The program “is running out of time and money to complete the planned flight testing and implement the required fixes and modifications” needed to finish the phase successfully, he said. “Flight testing is making progress but has fallen far behind the planned rate.”

The most complex software capabilities “are just being added” and new problems requiring fixes and verification testing “continue to be discovered at a substantial rate,” Gilmore wrote to Air Force Secretary Deborah Lee James; General David Goldfein, the service’s chief of staff; and Frank Kendall, the Pentagon’s acquisitions chief.


During a meeting with reporters in Singapore on Wednesday, James said the F-35 has “reached the point of initial combat capability, so that’s what we said we were going to have by now and we’ve got it. But ‘initial ’means initial and over the next several years it’s going to continue to develop, and the word ‘develop’ is an important word too.”

“If you go back over the entire history of the F-35 there is no question that over that history it’s taken longer and it has cost more money than originally anticipated but that is part and parcel of a development program,” she said.

Deploying Within a Year
While James said she wouldn’t be “at all surprised to see it deployed somewhere in the world over the next year or so,” Gilmore wrote in the memo that the F-35 could serve in combat today only if it was accompanied by older aircraft that would provide support to “locate and avoid modern threats, acquire targets and engage formations of enemy fighter aircraft due to outstanding performance deficiencies and limited weapons carriage.”

Joe DellaVedova, spokesman for the Defense Department’s F-35 program office, said in an e-mail that “there were absolutely no surprises” in the memo as “all of the issues mentioned are well-known” and being resolved.




Mark Johnson, a Lockheed spokesman, said in an e-mail that the Bethesda, Maryland-based contractor agreed with that assessment. “As the program has done in the past, we are confident it will continue to solve technical issues,” he said. “The U.S. Air Force and U.S. Marine Corps, who will take the jets into harm’s way if needed, state the jet is ready for combat, and there is no higher authority on the F-35’s performance than the warfighter.”


Gilmore cited at least 15 capabilities in the F-35’s most advanced software, known as 3F, that either have unresolved deficiencies or aren’t ready for testing. These include capabilities to process warnings of enemy ground and airborne radar signals that spot the fighter, to track moving targets on the ground, to share imagery between aircraft and to make use of the new Small Diameter Bomb.

In addition, all three models of the F-35 are “are at risk of not having a functioning and accurate gun” in time for the combat testing because “significant deficiencies discovered during initial testing” in 2015 “require multiple modifications” before accuracy testing can begin, he said.




http://www.bloomberg.com/news/artic...till-falls-short-pentagon-s-chief-tester-says
 
.
Gilmore is the head of the DoT&E. His department's report comes from the issues reported by the JPO, so when they say there are no surprises, that's because they reported it to him.

Its his job to go after every little issue that is normal within the developing cycle. Remember his criticism of the slow pace of weapons testing, and how at the rate it was going they would only be certified by 2021 or something like that? Then we had this.

http://www.edwards.af.mil/News/Arti...es-forward-with-record-breaking-weapons-tests

So clearly the program is taking care of the technical issues, and will continue to do so.
 
.