India’s first indigenous aircraft carrier to be inducted in 2018

sudhir007

SENIOR MEMBER
Joined
Jul 6, 2009
Messages
4,728
Reaction score
1
http://timesofindia.indiatimes.com/...-be-inducted-in-2018/articleshow/56023951.cms

The country's first indigenous aircraft carrier will be commissioned by the Indian Navy by the end of 2018, said Rear Admiral Surendra Ahuja, assistant controller carrier project and assistant controller warship production and acquisition, Integrated Headquarters, Ministry of Defence (Navy).

"The indigenous aircraft is currently being constructed in Cochin. It is expected to be delivered by the end of 2018," Ahuja told reporters on the sidelines of the passing out parade of 87th helicopter course of INS Rajjali at Arakkonam, Vellore.

As many as 11 Navy and five Coast Guard pilots were honoured with wings on Friday. It would have the capacity to carry 30 aircrafts, fighter flights and helicopters, he said.

The Indian Navy has sent a proposal to the central government, seeking its nod to build a bigger aircraft carrier, weighing 65,000 tonnes, with a capacity to carry 54 helicopters, fixed wing fighters and multi-role helicopters. "The proposal is currently with the government and is being actively considered. We are reasonably hopeful that we will get the approval very soon. It will be a game-changer," he said.

He further said the Indian Navy envisaged procuring 57 more technology-based fighters. "The proposal is yet to reach the government. The Navy is doing the ground work for the 57 tech-based aircrafts," he added.

The Navy has inducted eight P -8I (long-range maritime reconnaissance and anti-submarine warfare aircraft) in INS Rajali, he said and added that four more would be inducted soon. "We have signed the contract recently. It will be soon delivered," he said.

Of the contract signed with Russia for a total of 45 MiG - 29K aircrafts, the Navy had received 41 and the remaining four would be received within a month's time said Ahuja. "Twelve Dorniers, eight Chetak helicopters, 16 advanced lightweight helicopters, 16 multi-role helicopters and many more on the anvil," he added.

Earlier, speaking in the passing out parade, he said that the Navy and Coast Guard air arm have been expanding and were witnessing an unprecedented growth.

Addressing the pilots who received the 'wings', he advised them to remember that flying is good when there is a right mix of discipline and dare. He asked pilots to know their machine, craft and men for a rewarding career in the force.

The pilots underwent rigorous training for 21 weeks in flying and aviation at Indian Naval Air Squadron 561, the Helicopter Training School which has graduated 666 pilots for the Indian Navy and Coast Guard till date. The school was initially commissioned in Kochi on September 15, 1971 and it shifted the present location at INS Rajali in Arakkonam. It is the largest operational air base of the Indian Navy.

Lt Rishab Dutta received the Governor of Kerala rolling trophy after being adjudged the best all-round trainee pilot, while LT Kiran was awarded the Flag Officer Commanding-in-Chief Eastern Naval Command Rolling Trophy for standing first in order of merit. A book prize was also awarded to Lt Rishab Dutta for standing first in ground subjects. The graduate pilots will subsequently join operational flights in Daman, Goa, Kochi, Mumbai and Vizag.
 
.
When journalist will understand difference between delivery and commission:no:
 
. .
This rear admiral should be shot for lying through his teeth. :rofl::lol::D
 
. . .
This rear admiral should be shot for lying through his teeth. :rofl::lol::D

I think there is an issue with understanding and reporting by news correspondent, in all possibility, Admiral was talking of delivery of ship to customer, from there it should be another 18-24 months for commissioning.
 
. . .
Sea trials are next year. It will be commissioned in 2018.
Good to hear that.
Any idea on physical completion, most units (or modules) as these are referred to by CSL were in place and some deck related work is pending.
 
. .
I think there is an issue with understanding and reporting by news correspondent, in all possibility, Admiral was talking of delivery of ship to customer, from there it should be another 18-24 months for commissioning.
"The indigenous aircraft is currently being constructed in Cochin. It is expected to be delivered by the end of 2018," this is admiral exact quote , he is talking about delivery to navy . It will take some 1-2 years for commission after delivery.
 
.
It puzzles me why you guys even bother to believe this unrealistic deadline, considering your abysmal track records of on-time delivery? This is no way this carrier can be inducted before 2023.
 
.
It puzzles me why you guys even bother to believe this unrealistic deadline, considering your abysmal track records of on-time delivery? This is no way this carrier can be inducted before 2023.
By 2023 second vibrant will be out from yard.
 
.
"The indigenous aircraft is currently being constructed in Cochin. It is expected to be delivered by the end of 2018," this is admiral exact quote , he is talking about delivery to navy . It will take some 1-2 years for commission after delivery.
That is exactly, how i interpreted the statement. Induction imho is still 4 years away.

@nair can you put some light on how things are at the moment?
Google map shows the ship parked on Kollam waterway
upload_2016-12-17_15-55-58.png


But not sure, how old is the image.
 