What's new

First coal cargo reaches Payra

The Ronin

SENIOR MEMBER
Joined
Mar 24, 2017
Messages
3,386
Reaction score
0
Country
Bangladesh
Location
Bangladesh
1568955885.jpg


The first cargo of coal to be used for generating electricity at the 1,320-megawatt Payra coal-fired thermal power plant reached newly built Payra jetty on Thursday afternoon.

Chinese vessel Xin Hai Tong loaded with Indonesian coal reached Payra jetty at around 1:30 pm on the day, managing director of Bangladesh-China Power Company Ltd Md Khurshedul Alam told the FE.

He said this power plant will facilitate commissioning of the first 660-MW unit of the power plant.


The Chinese vessel carried around 200,000 tonnes of coal from Indonesian firm PT Bayan Resources Tbk, said Mr Alam.

It set sail for Bangladesh on September 10. The second coal cargo is expected to reach Payra jetty in October.

Officials said the construction work on the $1.98-billion power plant in Patuakhali is going on in full swing.

Around 85 per cent work on the under-construction facility, some 320 kilometres south off Dhaka and close to the proposed Payra seaport, has already been completed.

State-run Power Grid Company of Bangladesh Ltd has been working to complete a 400-kilovolt transmission line by September 30 to ease power evacuation from the plant.

The 1,320-MW Payra power plant would be the first such facility which will run on imported coal.

BCPCL, the project executor, has signed an agreement with the Indonesian supplier to annually import an estimated 4.0 million tonnes of coal for 10 years to operate it.

Coal price has been tagged with the Newcastle international coal price index having a discount of up to 60 per cent depending on the price movement.

Discount would increase if coal price shoots up globally and it would decrease if the price slides.

Initially, BCPCL will import directly from Indonesia with half-loaded 'Supramax' vessel having the volume of around 20,000 tonnes per cargo, said a BCPCL official.

After successful construction of transhipment facility in the Andaman, mother cargo vessel would be able to carry coal for the power plant, he added.

The first unit having 660-MW capacity at the power plant would go into operation by December 2019 and the second one having the same capacity by June 2020.

Some 13,000 tonnes of coal will be required per day to run the plant with full capacity.

It will use the best coal and apply ultra-supercritical technology with minimal environmental impacts, said a senior official of power division under the power, energy and mineral resources ministry.

BCPCL is a 50-50 joint venture between Bangladesh's NWPGCL and China National Machinery Import and Export Corporation (CMC).

BCPCL has been supplying 20 per cent equity to implement the project and the remaining 80 per cent is being sourced as loan from Exim Bank of China.

Bangladesh has issued a $1.0-billion worth of state guarantee in favour of the Chinese loan to this end.

It has allocated 998.77 acres of land to NWPGCL for the project on a turnkey basis by using eco-friendly ultra-supercritical technology.

The country started importing a huge quantity of hard black mineral to run the coal-fired power plant only due to non-availability of local coal.

It has five coal mines but extracts coal only from Barapukuria mine in Dinajpur, utilising the underground coal-mining method.

Barapukuria Coal Mining Company Ltd (BCMCL) annually extracts around 1.0 million tonnes, most of which is consumed by the nearby Barapukuria thermal power plant.

According to the power system master plan, officials said, the government expects to generate around 50 per cent of the local overall electricity from coal.

As planned, the government will have to generate around 12,000 megawatt of electricity from coal by 2024 while 20,000 MW by 2030 and 30,000 MW by 2041.

But the country has only three coal-fired plants having the total generation capacity of only 524 MW.

Currently, the government has been working on three major power generation hubs at Payra in Patuakhali, Maheshkhali and Matarbari in Cox's Bazar where several big import-based coal-fired power plants will be built.

The construction work on a 1,320 MW coal-fired power plant at Rampal in Bagerhat is also going on in full swing.

https://thefinancialexpress.com.bd/national/first-coal-cargo-reaches-payra-1568955885
 
.
When import is costly, coal-fired power plant generates costly power!
Mushfiqur Rahman | Published: May 22, 2019 20:59:40

1558537180.jpg
Photo: bdnews24.com

Bangladesh-India Friendship Power Company Limited (Rampal power plant) has invited international bids for coal transportation including transhipment for the 1320 MW coal-fired power plant at Rampal, Bagerhat. The international bidder is required to transport coal from designated load ports to offshore transhipment sites and arrange transhipment facilities to unload the coal and further transport it to the power plant site using self-propelled barges. The bidders are to submit their bidding documents by June 19, 2019.

The Bangladesh-India Friendship Power Company Limited (BIFPCL) is the first among three major under-construction coal-fired power plants in the coastal areas of Bangladesh (Matarbari 1200 MW, Payra 1320 MW and Rampal 1320 MW) to invite such bidding. Although it was said that the first 660 MW unit of the 1320 MW Payra power plant (BCPCL) would start producing power within 2019 with imported coal, power generation from Payra coal-fired power plant is likely to be delayed. Neither Payra nor Rampal power plants have their coal terminal ready and none of them has jetty or ports which can accommodate ocean going large coal carrying ships. Therefore, it is the only option for BCPCL (and Payra coal-fired power plant) to try to invite internationally experienced companies who can render services to the power company (NWPGCL-CMC China) to transport coal using both ocea- going ships (like Handimax, Panamax or Cape). The service company should also facilitate to unload coal at the open sea using transhipment facilities and further transport them by small self propelled barges to the plant site. Such barges should have the capacity to sail in the shallow waters from the sea to Harbaria channel and through the river systems to Rampal power plant jetty. The transportation is likely to be targeted from Indonesia (load port) to the power plant site. No doubt, the coal transportation cost will be high, especially for their multiple handling and for utilisation of mixed mode of transports. Also the Rampal and Payra coal-fired power plants will have to match their coal importation schedules with weather behaviour in the Bay of Bengal (notorious for its cyclone frequency). The Bay of Bengal hosts major atmospheric depressions and tropical cyclonic storms during May-November each year. Therefore, transhipment of coal from the large ocean-going vessels (with cargo carrying capacity of 40,000 tonnes to 120,000 tonnes) in the open sea to the small vessels has to be carefully planned to avoid demise of the cargo and the carriers. No doubt the international coal and bulk cargo transportation companies will add additional charges for the risky operations to deliver coal in the Bangladesh coast lines.

Unlike Payra and Rampal power plants, the Matarbari 1200 MW under-construction coal-fired power plant has included the excavation of a 14.3 km long, 250m wide and 18.5 meter deep channel and construction of a coal jetty in its contract signed in July 2017. The land development works for the power plant has been progressing and the first unit (600MW) of the power plant should come into operations in January 2024 followed by the second unit (600MW) in July 2014. As reported, 70 per cent work for land development and channel excavation has been completed and the coal jetty construction work would be completed in 2021. Once completed, the coal jetty can facilitate import of 4 (four) million tonnes of coal to feed the Matarbari 1200 MW power plant annually. With additional investment, the capacity of the coal jetty can be enhanced to facilitate larger volumes of coal import for supplying them using conveyor belts (for example, for the planned coal-fired power plant at Maheshkhali). The 18.5-metre deep and 250m-wide long channel will enable the Matarbari coal-fired power plant authority (Coal Power Generation Company Bangladesh Ltd-CPGBL) to import coal using ocean-going vessels having carrying capacity of 80,000-120,000 tonnes. Such large ships can significantly reduce coal-carrying costs and avoid the requirements for transhipment in the open sea.

It is a common knowledge that there is an additional cost involvement for operating coal-fired power plants due to the environmental concerns and compliance needs. However, public and private companies opt to use coal as major fuel for power generation due to its comparative cost advantages over LNG and liquid fuels. But due to certain limitations in planning and its implementation, two imported coal-based power plants, Payra and Rampal have proceeded without construction of coal terminal and port channel to allow large coal-carrying vessels. This may prove to be costly. This will result in the coal-fired power plants which import coal using small barges and involve transhipments and multiple handling, generating costly power.
 
.

Latest posts

Pakistan Defence Latest Posts

Back
Top Bottom