After Gorshkov, another Navy project hit by delay
NEW DELHI: The bad news for Navy shows no sign of stopping. The country's most ambitious ship-building project, construction of a 37,500-tonne indigenous aircraft carrier (IAC) at Cochin shipyard, is running way behind schedule. Sources said current projections show IAC will be ready for delivery to Navy earliest by 2015, after completion of construction and trials, instead of the earlier date of 2011-2012.
The IAC project, cleared by the government in January 2003 at a cost of Rs 3,261 crore after several years of dilly-dallying, is lagging behind on "almost all fronts".
"First, there was a big problem in getting 20,000 tonnes of special quality steel for it till SAIL stepped in. Then, there was a huge delay in procurement of bulb bars. Once these was sorted out, other problems crept in," a source said.
"The detailed designs and pre-production work also took a lot of time. As per revised plans, the keel of the warship was to be laid in October 2007 but this has been postponed by at least an year now. Consequently, the project cost will also go up substantially," he added.
All this will add to the woes of Navy, already grappling with huge delays in some big-ticket projects. The induction of the decommissioned Russian aircraft carrier Admiral Gorshkov, for instance, will not be possible before 2010. Rechristened INS Vikramaditya, this 44,570-tonne carrier was supposed to be operationally ready by August 2008, as per the Rs 6,900 crore package deal signed with Russia in January 2004.
Then, of course, there are slippages in the gigantic Rs 18,798 crore project to construct six Scorpene submarines at Mazagon Docks, slated for delivery between 2012 and 2017.
In the IAC project, the government has even signed two contracts worth 28 million Euros with Italian firm Fincantieri for design, integration, installation and commissioning of the IAC's propulsion system, apart from consultancy in detailed engineering and documentation.
"But despite the steel being cut at the Cochin shipyard in April 2005, the ship construction began only in November 2006," said the source.
To be charitable, one can argue this is the first time India is building an aircraft carrier, which has been the preserve of only US, UK, Russia and France so far.
With 160 officers and 1,400 sailors, the ship will be able to carry 12 MiG-29Ks, eight Tejas Light Combat Aircraft and 10 helicopters. Powered by four LM2500 gas turbines generating 80 MW, the carrier will be able to attain a maximum speed of 28 knots and be operationally deployed for 45 days at a stretch.
http://timesofindia.indiatimes.com/articleshow/msid-2269772,prtpage-1.cms
NEW DELHI: The bad news for Navy shows no sign of stopping. The country's most ambitious ship-building project, construction of a 37,500-tonne indigenous aircraft carrier (IAC) at Cochin shipyard, is running way behind schedule. Sources said current projections show IAC will be ready for delivery to Navy earliest by 2015, after completion of construction and trials, instead of the earlier date of 2011-2012.
The IAC project, cleared by the government in January 2003 at a cost of Rs 3,261 crore after several years of dilly-dallying, is lagging behind on "almost all fronts".
"First, there was a big problem in getting 20,000 tonnes of special quality steel for it till SAIL stepped in. Then, there was a huge delay in procurement of bulb bars. Once these was sorted out, other problems crept in," a source said.
"The detailed designs and pre-production work also took a lot of time. As per revised plans, the keel of the warship was to be laid in October 2007 but this has been postponed by at least an year now. Consequently, the project cost will also go up substantially," he added.
All this will add to the woes of Navy, already grappling with huge delays in some big-ticket projects. The induction of the decommissioned Russian aircraft carrier Admiral Gorshkov, for instance, will not be possible before 2010. Rechristened INS Vikramaditya, this 44,570-tonne carrier was supposed to be operationally ready by August 2008, as per the Rs 6,900 crore package deal signed with Russia in January 2004.
Then, of course, there are slippages in the gigantic Rs 18,798 crore project to construct six Scorpene submarines at Mazagon Docks, slated for delivery between 2012 and 2017.
In the IAC project, the government has even signed two contracts worth 28 million Euros with Italian firm Fincantieri for design, integration, installation and commissioning of the IAC's propulsion system, apart from consultancy in detailed engineering and documentation.
"But despite the steel being cut at the Cochin shipyard in April 2005, the ship construction began only in November 2006," said the source.
To be charitable, one can argue this is the first time India is building an aircraft carrier, which has been the preserve of only US, UK, Russia and France so far.
- But almost all defence projects of India suffer from huge time and cost overruns, underlining the lack of proper planning.
With 160 officers and 1,400 sailors, the ship will be able to carry 12 MiG-29Ks, eight Tejas Light Combat Aircraft and 10 helicopters. Powered by four LM2500 gas turbines generating 80 MW, the carrier will be able to attain a maximum speed of 28 knots and be operationally deployed for 45 days at a stretch.